7099-7101 N FALLBROOK AVE 91307
Certificate Information: 7099-7101 N FALLBROOK AVE 91307
- Application / Permit
- 21016-20000-58286
- Plan Check / Job No.
- B21VN17483
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT 20' X 20'-2" PORTION OF SINGLE FAMILY DWELLING TO JUNIOR ACCESSORY DWELLING UNIT (360 SQ FT) PER GCS 65852.2(e)(1)(A) and 65852.22
- Permit Issued
- Issued on 1/20/2022
- Issuing Office
- Current Status
- CofO Issued on 6/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 12/24/2021 | JEROME MAGAT PALMA |
| Plan Check Approved | 1/19/2022 | JEROME MAGAT PALMA |
| Issued | 1/20/2022 | APPLICANT |
| Building Plans Picked Up | 3/22/2022 | APPLICANT |
| CofO in Progress | 5/23/2022 | CHRIS CHRISTENSEN |
| Permit Finaled | 6/15/2022 | JOHN JANSON |
| CofO Issued | 6/15/2022 | JOHN JANSON |
| Permit Finaled | 6/15/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/4/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/4/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 1/5/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 2/14/2022 | Corrections Issued | STEVEN BACK |
| Final | 2/14/2022 | Not Ready for Inspection | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 2/14/2022 | SGSOV Not Ready | STEVEN BACK |
| Smoke Detectors | 2/14/2022 | Not Ready for Inspection | STEVEN BACK |
| Interior/Exterior Lathing | 4/25/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Wood Frame | 4/25/2022 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 5/2/2022 | Approved | CHRIS CHRISTENSEN |
| Insulation | 5/2/2022 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 5/5/2022 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 5/5/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| HVAC-Final | 5/5/2022 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 5/5/2022 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 5/11/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 5/11/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 5/11/2022 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 5/11/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 5/20/2022 | OK to Issue CofO | CHRIS CHRISTENSEN |