8148 N POTTER AVE 91605
Certificate Information: 8148 N POTTER AVE 91605
- Application / Permit
- 21016-20000-58269
- Plan Check / Job No.
- B21VN17467
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)-(d).
- Permit Issued
- Issued on 3/9/2022
- Issuing Office
- Current Status
- CofO Issued on 8/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2021 | SERGIO MUNIZ |
| Corrections Issued | 12/24/2021 | SERGIO MUNIZ |
| Plan Check Approved | 3/9/2022 | SERGIO MUNIZ |
| Issued | 3/9/2022 | APPLICANT |
| Building Plans Picked Up | 3/10/2022 | APPLICANT |
| CofO in Progress | 7/7/2022 | CHRISTOPHER DELLEFIELD |
| Permit Finaled | 8/20/2022 | DANIEL ORRANTE |
| CofO Issued | 8/20/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/20/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 12/29/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/29/2021 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 12/29/2021 | JOSE DUARTE-DIAZ |
| Construction near power lines | Cleared | 3/9/2022 | JOHN BACON |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/13/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 4/13/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 4/13/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Sewer | 4/13/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Excavation/Setback/Form/Re-Bar | 4/19/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 4/19/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Sewer | 4/19/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 5/5/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 5/5/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 5/5/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 5/5/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| MERV13>=Rough | 5/5/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 5/5/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 5/9/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 5/9/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 5/9/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 5/9/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 5/9/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 5/12/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 5/16/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 5/16/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Wood Frame | 5/16/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 5/20/2022 | Approved | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 5/20/2022 | Corrections Issued | DEANDRE HOFFMAN |
| Shower Pan | 5/20/2022 | Approved | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 5/24/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 5/31/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 7/1/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 7/1/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Green Building Final | 7/1/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 7/1/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| MERV13>=Final | 7/1/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 7/1/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 7/1/2022 | SGSOV Not Ready | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 7/1/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 7/7/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 7/7/2022 | OK to Issue CofO | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 7/7/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 7/7/2022 | Approved | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 7/7/2022 | SGSOV Approved | CHRISTOPHER DELLEFIELD |