14632 W CHATSWORTH ST 91345

Certificate Information: 14632 W CHATSWORTH ST 91345

Application / Permit
21016-20000-58100
Plan Check / Job No.
B21VN17359
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT (682 SQ FT) PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 3/1/2022
Issuing Office
Current Status
CofO Issued on 4/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/15/2021 APPLICANT
Assigned to Plan Check Engineer 12/23/2021 JEROME MAGAT PALMA
Corrections Issued 12/24/2021 JEROME MAGAT PALMA
Plan Check Approved 2/28/2022 JEROME MAGAT PALMA
Issued 3/1/2022 APPLICANT
Building Plans Picked Up 3/3/2022 APPLICANT
CofO in Progress 3/24/2023 JENNIFER RABUCHIN
CofO Issued 4/25/2023 MICHAEL SMITH
Permit Finaled 4/25/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/30/2021 ABDULLAH SADOZAI
Sewer availability Cleared 12/30/2021 ABDULLAH SADOZAI
Eng Process Fee Ord 176,300 Cleared 2/7/2022 ABDULLAH SADOZAI

Contact Information

Contractor Owner-Builder       ,
Engineer Mohammadi,, Saeid; Lic. No.: C82330 17412 VENTUTRA BLVD 21      ENCINO, CA 91316

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/9/2022 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 5/9/2022 Corrections Issued JENNIFER RABUCHIN
Deputy Drilled-In Anchors 8/4/2022 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 8/23/2022 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 8/23/2022 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 8/31/2022 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 8/31/2022 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 10/25/2022 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 10/25/2022 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 10/25/2022 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 10/25/2022 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 10/25/2022 Not Ready for Inspection JENNIFER RABUCHIN
MERV13>=Rough 10/25/2022 Not Ready for Inspection JENNIFER RABUCHIN
METHANE-Rough 10/25/2022 Approved JENNIFER RABUCHIN
PLUMBING-Rough 10/25/2022 Corrections Issued JENNIFER RABUCHIN
Deputy Wood Construction 10/27/2022 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 10/31/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 10/31/2022 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 10/31/2022 Approved JENNIFER RABUCHIN
Green Building Rough 10/31/2022 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 10/31/2022 Approved JENNIFER RABUCHIN
MERV13>=Rough 10/31/2022 Approved JENNIFER RABUCHIN
PLUMBING-Rough 10/31/2022 Approved JENNIFER RABUCHIN
Rough-Elec/Plmb/HVAC 10/31/2022 Approved JENNIFER RABUCHIN
Underground Mechanical 10/31/2022 Partial Approval JENNIFER RABUCHIN
Wood Frame 10/31/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 11/9/2022 Partial Approval JENNIFER RABUCHIN
Shower Pan 11/9/2022 Approved JENNIFER RABUCHIN
Insulation 11/21/2022 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 11/21/2022 Partial Approval JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 11/21/2022 SGSOV Approved JENNIFER RABUCHIN
Drywall Nailing 12/7/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 12/7/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 2/16/2023 Partial Inspection KRISTEN CAUSEY
Final 2/16/2023 Partial Inspection KRISTEN CAUSEY
Green Building Final 2/16/2023 Partial Inspection KRISTEN CAUSEY
Green Building Rough 2/16/2023 Partial Inspection KRISTEN CAUSEY
MERV13>=Final 2/16/2023 Partial Inspection KRISTEN CAUSEY
Smoke Detectors 2/16/2023 Partial Inspection KRISTEN CAUSEY
BUILDING-Rough-Frame 3/24/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 3/24/2023 Approved JENNIFER RABUCHIN
Final 3/24/2023 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 3/24/2023 Approved JENNIFER RABUCHIN
Green Building Rough 3/24/2023 Approved JENNIFER RABUCHIN
HVAC-Final 3/24/2023 Approved JENNIFER RABUCHIN
MERV13>=Final 3/24/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 3/24/2023 Approved JENNIFER RABUCHIN
Smoke Detectors 3/24/2023 Approved JENNIFER RABUCHIN