12169 W VENTURA BLVD 91604

Certificate Information: 12169 W VENTURA BLVD 91604

Application / Permit
21016-20000-58020
Plan Check / Job No.
B21VN17311
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Massage Parlor
Work Description
ePLAN. CHANGE OF USE FROM RETAIL TO MASSAGE PARLOR. INTERIOR TENANT IMPROVEMENT.
Permit Issued
Issued on 4/7/2022
Issuing Office
Current Status
CofO Issued on 10/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2021 APPLICANT
Assigned to Plan Check Engineer 12/26/2021 KEVIN MORALES
Corrections Issued 12/27/2021 KEVIN MORALES
Quality Review Completed 12/27/2021 PRANITA SHAH
Applicant returned to address corrections 3/18/2022 KEVIN MORALES
Plan Check Approved 4/7/2022 KEVIN MORALES
Issued 4/7/2022 APPLICANT
CofO in Progress 10/11/2023 ROBERT DAVIS
Permit Finaled 10/11/2023 JEFFREY DURAN
CofO Issued 10/11/2023 JEFFREY DURAN
Permit Finaled 10/11/2023 JEFFREY DURAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/4/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 1/5/2022 DAGOVERTO GUERRERO
ZA Case Cleared 3/17/2022 LAUREN PADICK
ZA Case Cleared 3/17/2022 LAUREN PADICK
ZI Cleared 3/17/2022 LAUREN PADICK
Specific Plan Cleared 3/30/2022 ERIN NASH

Contact Information

Contractor Sca General Contracting Inc; Lic. No.: 981061-B       ,
Engineer Fernandez,, Terry Lynn; Lic. No.: S3256 1719 CARVER ST      REDONDO BEACH, CA 90278

Inspector Information

JEFFREY FULTON, (818) 374-1132 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/13/2022 Conditional Approval ROBERT DAVIS
Insulation 10/25/2022 Partial Inspection ANDREW DORSO
Wood Frame 12/29/2022 Partial Approval BRIAN KELLY
Insulation 1/20/2023 Approved DANIEL VARNUM
Light Gage Steel Frame 3/8/2023 Partial Approval ANDREW DORSO
Drywall Nailing 3/13/2023 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 3/16/2023 Partial Approval STEVEN LEVITT
Drywall Nailing 4/20/2023 Approved ROBERT DAVIS
Interior/Exterior Lathing 4/20/2023 Approved ROBERT DAVIS
Light Gage Steel Frame 4/20/2023 Approved ROBERT DAVIS
Partition/T-Bar Ceiling 6/22/2023 Partial Inspection ROBERT DAVIS
Final 9/25/2023 OK to Issue CofO ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 9/25/2023 SGSOV Approved ROBERT DAVIS
Smoke Detectors 9/25/2023 Approved ROBERT DAVIS