2116 S COCHRAN AVE 90016

Certificate Information: 2116 S COCHRAN AVE 90016

Application / Permit
21016-20000-57979
Plan Check / Job No.
B21VN17293
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) TWO CAR DETACHED GARAGE AND STORAGE INTO A (N) ACCESSORY DWELLING UNIT, (20'-0"x24'-0"), 451 SQFT PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 3/29/2022
Issuing Office
Current Status
CofO Issued on 3/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/14/2021 APPLICANT
Assigned to Plan Check Engineer 12/22/2021 PETER MOSESIAN
Corrections Issued 12/26/2021 PETER MOSESIAN
Building Plans Picked Up 12/29/2021 APPLICANT
Issued 3/29/2022 APPLICANT
CofO in Progress 1/20/2023 JOSE AVILA
Permit Finaled 3/4/2023 DANIEL ORRANTE
CofO Issued 3/4/2023 DANIEL ORRANTE
Permit Finaled 3/4/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 12/29/2021 CELINA MORENO
Sewer availability Cleared 12/29/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 1/4/2022 CELINA MORENO
Construction near power lines Cleared 3/12/2022 RIDWAN HARDY

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor Preferred Home Builders Inc; Lic. No.: 773147-B 21204 VANOWEN STREET      CANOGA PARK, CA 91303

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/30/2022 Conditional Approval JOSE AVILA
Underground Mechanical 3/31/2022 Partial Approval JOSE AVILA
Footing/Foundation/Slab 4/1/2022 Partial Inspection JOSE AVILA
Footing/Foundation/Slab 4/14/2022 Approved JOSE AVILA
Underground Mechanical 4/20/2022 Approved JOSE AVILA
PLUMBING-Rough 4/22/2022 Corrections Issued JOSE AVILA
Wood Frame 4/22/2022 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 5/2/2022 Partial Approval JOSE AVILA
Green Building Rough 5/2/2022 Not Ready for Inspection JOSE AVILA
Rough-Elec/Plmb/HVAC 5/2/2022 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 5/4/2022 Approved JOSE AVILA
ELECTRICAL-Rough 5/4/2022 Approved JOSE AVILA
Green Building Rough 5/4/2022 Approved JOSE AVILA
Sewer 5/5/2022 Approved JOSE AVILA
Insulation 5/9/2022 Approved JOSE AVILA
Interior/Exterior Lathing 5/9/2022 Approved JOSE AVILA
Shower Pan 5/9/2022 Approved JOSE AVILA
Drywall Nailing 5/12/2022 Approved JOSE AVILA
Drywall Nailing 5/12/2022 Approved SHAVONNE ESPINOZA
Interior/Exterior Lathing 5/12/2022 Approved JOSE AVILA
Final 6/28/2022 Corrections Issued JOSE AVILA
Green Building Final 6/28/2022 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 6/28/2022 SGSOV Not Ready JOSE AVILA
Smoke Detectors 6/28/2022 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 7/28/2022 SGSOV Not Ready FREDDIE RIVERA
Final 8/5/2022 Corrections Issued JOSE AVILA
Green Building Final 8/5/2022 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 8/5/2022 SGSOV Approved JOSE AVILA
Final 8/10/2022 Partial Approval JOSE AVILA
Final 1/19/2023 OK to Issue CofO JOSE AVILA