15108 W WEDDINGTON ST 91411

Certificate Information: 15108 W WEDDINGTON ST 91411

Application / Permit
21016-20000-57917
Plan Check / Job No.
B21VN17249
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) (18'-6"x33'-2"), 564 DETACHED GARAGE W/WORKSHOP INTO A (N) ACCESSORY DWELLING UNIT. PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 6/3/2022
Issuing Office
Metro
Current Status
CofO Issued on 6/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/13/2021 APPLICANT
Assigned to Plan Check Engineer 12/21/2021 PETER MOSESIAN
Corrections Issued 1/12/2022 PETER MOSESIAN
Applicant returned to address corrections 5/5/2022 PETER MOSESIAN
Plan Check Approved 5/16/2022 PETER MOSESIAN
Issued 6/3/2022 APPLICANT
CofO in Progress 6/2/2023 THOMAS FINNILA
CofO in Progress 6/2/2023 THOMAS FINNILA
Permit Finaled 6/8/2023 MICHAEL SMITH
CofO Issued 6/8/2023 MICHAEL SMITH
Permit Finaled 6/8/2023 MICHAEL SMITH

Permit Application Clearance Information

ZI Cleared 2/1/2022 MIGUEL GAMBOA
Address approval Cleared 2/2/2022 AMIR KASHFI
Sewer availability Cleared 2/2/2022 AMIR KASHFI
Eng Process Fee Ord 176,300 Cleared 2/8/2022 AMIR KASHFI

Contact Information

Architect Lopez,, Craig Joseph; Lic. No.: C14263 155 GRANADA ST STE "L"      CAMARILLO, CA 93010
Contractor Pro Restoration Contractors Inc; Lic. No.: 1005654-B 9461 WISH AVENUE      NORTHRIDGE, CA 91325

Inspector Information

JACK KARGODORIAN, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/5/2022 Not Ready for Inspection JACK KARGODORIAN
Underground Mechanical 12/13/2022 Not Ready for Inspection JENNIFER RABUCHIN
Deputy Drilled-In Anchors 12/16/2022 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 12/16/2022 Corrections Issued THOMAS FINNILA
Underground Mechanical 12/16/2022 Conditional Approval THOMAS FINNILA
Deputy Drilled-In Anchors 12/20/2022 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 12/21/2022 Partial Approval CHRISTOPHER DELLEFIELD
Underground Mechanical 12/21/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Deputy Drilled-In Anchors 1/12/2023 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 1/12/2023 Not Ready for Inspection THOMAS FINNILA
Wood Frame 1/17/2023 Corrections Issued THOMAS FINNILA
BUILDING-Rough-Frame 1/30/2023 Not Ready for Inspection JACK KARGODORIAN
ELECTRICAL-Rough 1/30/2023 Corrections Issued JACK KARGODORIAN
Green Building Rough 1/30/2023 Not Ready for Inspection JACK KARGODORIAN
HVAC-Rough 1/30/2023 Not Ready for Inspection JACK KARGODORIAN
PLUMBING-Rough 1/30/2023 Not Ready for Inspection JACK KARGODORIAN
BUILDING-Rough-Frame 2/3/2023 Not Ready for Inspection JOHN COLEMAN
ELECTRICAL-Rough 2/3/2023 Corrections Issued JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 2/3/2023 Partial Approval JOHN COLEMAN
Green Building Rough 2/3/2023 Corrections Issued JOHN COLEMAN
HVAC-Rough 2/3/2023 Approved JOHN COLEMAN
PLUMBING-Rough 2/3/2023 Not Ready for Inspection JOHN COLEMAN
ELECTRICAL-Rough 2/10/2023 Conditional Approval THOMAS FINNILA
Wood Frame 2/10/2023 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Rough 2/15/2023 Approved THOMAS FINNILA
PLUMBING-Rough 2/15/2023 Partial Approval THOMAS FINNILA
Wood Frame 2/15/2023 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 2/23/2023 Not Ready for Inspection THOMAS FINNILA
Green Building Rough 2/23/2023 Not Ready for Inspection THOMAS FINNILA
Interior/Exterior Lathing 2/23/2023 Not Ready for Inspection THOMAS FINNILA
Interior/Exterior Lathing 2/27/2023 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 2/28/2023 Approved THOMAS FINNILA
Green Building Rough 2/28/2023 Approved THOMAS FINNILA
Interior/Exterior Lathing 2/28/2023 Not Ready for Inspection THOMAS FINNILA
Insulation 3/9/2023 Approved JOHN COLEMAN
Interior/Exterior Lathing 3/9/2023 Approved JOHN COLEMAN
Drywall Nailing 3/14/2023 Approved THOMAS FINNILA
ELECTRICAL-Final 4/21/2023 Not Ready for Inspection THOMAS FINNILA
Service/Power Release 4/21/2023 Not Ready for Inspection THOMAS FINNILA
Final 5/23/2023 Corrections Issued THOMAS FINNILA
Green Building Final 5/23/2023 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 5/23/2023 SGSOV Approved THOMAS FINNILA
Smoke Detectors 5/23/2023 Approved THOMAS FINNILA
Final 5/30/2023 OK to Issue CofO THOMAS FINNILA