10132 N MEMORY PARK AVE 91345
Certificate Information: 10132 N MEMORY PARK AVE 91345
- Application / Permit
- 21016-20000-57516
- Plan Check / Job No.
- B21VN17162
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* CONVERT (E) 2-CAR GARAGE TO ADU AND ADD (204 SF) PER CA GC 65852.2(e)(1)(B) AND LAMC 12.22.A.33(c)-(d), (g). COMPLY WITH DEPARTMENT ORDER effective date 07/23/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 6/29/2022
- Issuing Office
- Current Status
- CofO Issued on 4/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/17/2021 | VIVIAN LAO |
| Corrections Issued | 12/17/2021 | VIVIAN LAO |
| Applicant returned to address corrections | 4/5/2022 | VIVIAN LAO |
| Plan Check Approved | 5/25/2022 | VIVIAN LAO |
| Issued | 6/29/2022 | APPLICANT |
| CofO in Progress | 3/14/2025 | DAVID ANDERSON |
| No Progress | 3/27/2025 | DAVID MATSON |
| CofO in Progress | 3/27/2025 | DAVID MATSON |
| Permit Finaled | 4/15/2025 | RUBEN SALAS |
| CofO Issued | 4/15/2025 | RUBEN SALAS |
| Permit Finaled | 4/15/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/9/2022 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 3/9/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/2/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 4/2/2022 | JOSE DUARTE-DIAZ |
| Construction near power lines | Cleared | 4/13/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lopez,, Mauricio Jose; Lic. No.: C36801 | 1391 N THIRD AVE UPLAND, CA 91786 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/27/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/11/2023 | Partial Approval | DAVID MATSON |
| Deputy Drilled-In Anchors | 8/15/2023 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 8/18/2023 | Approved | DAVID ANDERSON |
| Deputy Wood Construction | 9/5/2023 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2023 | Approved | DAVID ANDERSON |
| Green Building Rough | 9/5/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 10/24/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/24/2023 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 11/8/2023 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 11/8/2023 | Partial Approval | CHRISTOPHER ROJAS |
| PLUMBING-Final | 11/8/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 11/8/2023 | Approved | CHRISTOPHER ROJAS |
| Rough-Elec/Plmb/HVAC | 11/8/2023 | Approved | CHRISTOPHER ROJAS |
| Sewer | 11/8/2023 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 11/22/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Test | 11/22/2023 | Partial Approval | JENNIFER RABUCHIN |
| HVAC-Rough | 11/22/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Wood Frame | 11/22/2023 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 11/29/2023 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 11/29/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 11/29/2023 | Approved | JENNIFER RABUCHIN |
| Insulation | 11/29/2023 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 12/11/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 2/6/2024 | Approved | MATTHEW NELSON |
| Shower Pan | 2/6/2024 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 1/31/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 1/31/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 1/31/2025 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 1/31/2025 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 1/31/2025 | Approved | JENNIFER RABUCHIN |
| Final | 2/12/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 3/13/2025 | OK to Issue CofO | DAVID ANDERSON |
| Special/Order Compliance | 3/13/2025 | Corrections Issued | DAVID ANDERSON |
| Pre-Inspection | 3/19/2025 | Partial Inspection | ROBERT GOLD |
| Special/Order Compliance | 4/7/2025 | Approved | JENNIFER RABUCHIN |