3447 W GREENSWARD ROAD 90039

Certificate Information: 3447 W GREENSWARD ROAD 90039

Application / Permit
21016-20000-57444
Plan Check / Job No.
B21VN17120
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR AND EXTRIOR REMODEL SFD AND UNDERPIN (E) FIUNDATION
Permit Issued
Issued on 4/5/2022
Issuing Office
Current Status
Permit Finaled on 9/25/2024

Permit Application Status History

Submitted 12/11/2021 APPLICANT
Assigned to Plan Check Engineer 12/29/2021 MOHAMMAD ESMAILI
Corrections Issued 1/2/2022 MOHAMMAD ESMAILI
Quality Review Completed 1/4/2022 OMID HEDAYAT
Building Plans Picked Up 1/5/2022 APPLICANT
Plan Check Approved 3/21/2022 MOHAMMAD ESMAILI
Issued 4/5/2022 APPLICANT
Permit Finaled 9/24/2024 HAMIK HARTOUNIAN

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/26/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 2/26/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 2/28/2022 CHRISTOPHER ROCHA

Contact Information

Contractor Mr Fix Inc; Lic. No.: 932510-B 6000 YORK BLVD STE A      LOS ANGELES, CA 90042
Engineer Franceschi,, Paul; Lic. No.: S4309 2388 KENILWORTH AVE      LOS ANGELES, CA 90039

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/28/2022 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 5/4/2022 Corrections Issued HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 5/5/2022 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 5/6/2022 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 5/18/2022 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 7/7/2022 Approved HAMIK HARTOUNIAN
HVAC-Rough 7/7/2022 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 7/7/2022 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 7/27/2022 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 8/4/2022 Approved HAMIK HARTOUNIAN
HVAC-Rough 8/4/2022 Conditional Approval HAMIK HARTOUNIAN
HVAC-Rough 8/15/2022 Partial Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 8/15/2022 Approved HAMIK HARTOUNIAN
Shower Pan 8/15/2022 Conditional Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 8/19/2022 Approved CHARLES BOGHOSKHAN
BUILDING-Rough-Frame 8/26/2022 Conditional Approval HAMIK HARTOUNIAN
Insulation 8/26/2022 Conditional Approval HAMIK HARTOUNIAN
Drywall Nailing 9/2/2022 Approved RUBEN SALAS
Insulation 9/2/2022 Approved RUBEN SALAS
Wood Frame 9/2/2022 Approved RUBEN SALAS
Final 5/17/2024 Corrections Issued THOMAS LOGRASSO
Green Building Final 5/17/2024 Not Ready for Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 5/17/2024 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 5/17/2024 Approved THOMAS LOGRASSO
Final 5/31/2024 Not Ready for Inspection THOMAS LOGRASSO
Final 9/24/2024 Permit Finaled HAMIK HARTOUNIAN