3313 S COLBERT AVE 90066
Certificate Information: 3313 S COLBERT AVE 90066
- Application / Permit
- 21016-20000-57186
- Plan Check / Job No.
- B21VN16979
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) (18'-1"x20'-0"), 362 SQ. FT. DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER CA GOVT. CODE 65852.2(e)(1)(A)
- Permit Issued
- Issued on 4/28/2022
- Issuing Office
- Current Status
- CofO Issued on 6/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2021 | PETER MOSESIAN |
| Corrections Issued | 12/20/2021 | PETER MOSESIAN |
| Building Plans Picked Up | 12/29/2021 | APPLICANT |
| Plan Check Approved | 3/23/2022 | PETER MOSESIAN |
| Issued | 4/28/2022 | APPLICANT |
| CofO in Progress | 6/7/2023 | JOHNNY MIRANDA |
| CofO in Progress | 6/7/2023 | JOHNNY MIRANDA |
| Permit Finaled | 6/8/2023 | DANIEL ORRANTE |
| CofO Issued | 6/8/2023 | DANIEL ORRANTE |
| Permit Finaled | 6/8/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 1/10/2022 | SAUL GARCIA |
| Sewer availability | Cleared | 1/10/2022 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 1/12/2022 | SAUL GARCIA |
| Specific Plan | Cleared | 2/22/2022 | PEDRO AYALA |
| Construction near power lines | Cleared | 3/13/2022 | TINA MIRANDA |
Contact Information
| Contractor | Diditan Group Inc; Lic. No.: 1008348-B | 5632 VAN NUYS BLVD STE 305 SHERMAN OAKS, CA 91401 |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/24/2022 | Partial Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 7/5/2022 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Rough | 7/5/2022 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 9/12/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Gas Test | 9/12/2022 | Partial Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 9/14/2022 | Corrections Issued | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 9/29/2022 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 12/22/2022 | Corrections Issued | JOHNNY MIRANDA |
| Insulation | 1/9/2023 | Corrections Issued | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 1/11/2023 | Partial Approval | CLAYTON GRAHAM |
| HVAC-Rough | 1/13/2023 | Approved | JOHNNY MIRANDA |
| Insulation | 1/13/2023 | Approved | JOHNNY MIRANDA |
| Insulation | 1/19/2023 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 1/30/2023 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 1/30/2023 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 2/1/2023 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 4/21/2023 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 4/21/2023 | Corrections Issued | EVAN COOPER |
| Final | 4/21/2023 | Corrections Issued | EVAN COOPER |
| Green Building Final | 4/21/2023 | Approved | EVAN COOPER |
| HVAC-Final | 4/21/2023 | Corrections Issued | EVAN COOPER |
| PLUMBING-Final | 4/21/2023 | Corrections Issued | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 4/21/2023 | SGSOV Not Ready | EVAN COOPER |
| Smoke Detectors | 4/21/2023 | Approved | EVAN COOPER |
| Final | 5/4/2023 | Corrections Issued | JOHNNY MIRANDA |
| Final | 5/5/2023 | Corrections Issued | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 5/5/2023 | SGSOV Approved | JOHNNY MIRANDA |
| Final | 5/15/2023 | OK to Issue CofO | JOHNNY MIRANDA |