717 W TEMPLE ST 90012
Certificate Information: 717 W TEMPLE ST 90012
- Application / Permit
- 21016-20000-57177
- Plan Check / Job No.
- B21VN16963
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- INSTALL ROOFTOP PV SYSTEM
- Permit Issued
- Issued on 8/29/2022
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 12/12/2022
Permit Application Status History
| Submitted | 12/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2022 | MOHAMMAD ESMAILI |
| Corrections Issued | 1/27/2022 | MOHAMMAD ESMAILI |
| Quality Review Completed | 2/4/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 2/10/2022 | APPLICANT |
| Applicant returned to address corrections | 4/6/2022 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 5/16/2022 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 7/11/2022 | MOHAMMAD ESMAILI |
| Plan Check Approved | 8/24/2022 | MOHAMMAD ESMAILI |
| Issued | 8/29/2022 | APPLICANT |
| Permit Finaled | 12/2/2022 | TIMOTHY BUXTON |
Permit Application Clearance Information
| "D" conditions | Cleared | 3/9/2022 | PABLO ESTRADA |
| Miscellaneous | Cleared | 3/9/2022 | PABLO ESTRADA |
| ZA Case | Cleared | 3/9/2022 | PABLO ESTRADA |
| ZA Case | Cleared | 3/9/2022 | PABLO ESTRADA |
| ZA Case | Cleared | 3/9/2022 | PABLO ESTRADA |
| ZI | Cleared | 3/9/2022 | PABLO ESTRADA |
| Miscellaneous | Cleared | 3/14/2022 | WILLIAM JOHNS |
Contact Information
| Contractor | O'Bryant Electric Inc; Lic. No.: 386619-C10 | 9314 ETON AVENUE CHATSWORTH, CA 91311 |
| Engineer | Zacher,, Paul; Lic. No.: S3878 | 1478 STONE PT DR 190 ROSEVILLE, CA 95661 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 12/2/2022 | Permit Finaled | TIMOTHY BUXTON |
| METHANE-Final | 12/2/2022 | Approved | TIMOTHY BUXTON |
| METHANE-Rough | 12/2/2022 | Approved | TIMOTHY BUXTON |
| Reinforced Masonry Frame | 12/2/2022 | Approved | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 12/2/2022 | SGSOV No Gas | TIMOTHY BUXTON |
| Smoke Detectors | 12/2/2022 | Approved | TIMOTHY BUXTON |