21800 W VICTORY BLVD 91367
Certificate Information: 21800 W VICTORY BLVD 91367
- Application / Permit
- 21016-20000-57111
- Plan Check / Job No.
- B21VN16912
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- TENANT IMPROVEMENT TO (E) OPTICAL SERVICE AREA IN COSTCO.
- Permit Issued
- Issued on 4/18/2022
- Issuing Office
- Current Status
- Permit Finaled on 1/31/2023
Permit Application Status History
| Submitted | 12/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2021 | JOE VO |
| Corrections Issued | 12/31/2021 | JOE VO |
| Quality Review Completed | 1/3/2022 | LIPING TENG |
| Applicant returned to address corrections | 1/25/2022 | JOE VO |
| Applicant returned to address corrections | 3/1/2022 | JOE VO |
| Plan Check Approved | 3/28/2022 | JOE VO |
| Issued | 4/18/2022 | APPLICANT |
| Permit Finaled | 1/31/2023 | CAMERON CHABAN |
Permit Application Clearance Information
| DAS Clearance | Cleared | 3/17/2022 | JOE VO |
Contact Information
| Contractor | Harvey Usa Llc; Lic. No.: 866177-B | 9455 RIDGEHAVEN COURT STE 200 SAN DIEGO, CA 92123 |
| Engineer | Wampler,, Thomas Arthur; Lic. No.: S5334 | 9725 THIRD AVE NE STE207 SEATTLE, WA 98115 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/1/2022 | Conditional Approval | ANDREW DORSO |
| Light Gage Steel Frame | 6/1/2022 | Not Ready for Inspection | KENNETH ROBERTS |
| Light Gage Steel Frame | 6/3/2022 | Corrections Issued | DANIEL VARNUM |
| Drywall Nailing | 6/7/2022 | Approved | CAMERON CHABAN |
| T-Bar Ceiling | 6/22/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Final | 6/30/2022 | Not Ready for Inspection | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 6/30/2022 | SGSOV Approved | ROBERT DAVIS |
| Smoke Detectors | 6/30/2022 | Approved | ROBERT DAVIS |
| Deputy Drilled-In Anchors | 7/12/2022 | Conditional Approval | JEFFREY DURAN |
| Light Gage Steel Frame | 7/13/2022 | Approved | DANIEL VARNUM |
| Drywall Nailing | 7/15/2022 | Approved | BRUCE CAMPBELL |
| T-Bar Ceiling | 8/10/2022 | Not Ready for Inspection | DANIEL VARNUM |
| T-Bar Ceiling | 8/18/2022 | Approved | DANIEL VARNUM |
| Final | 11/10/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Final | 11/18/2022 | Not Ready for Inspection | KENNETH ROBERTS |
| Final | 11/28/2022 | Partial Inspection | CAMERON CHABAN |