22706-22708 W ENADIA WAY 91307
Certificate Information: 22706-22708 W ENADIA WAY 91307
- Application / Permit
- 21016-20000-56944
- Plan Check / Job No.
- B21VN16830
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 22' 7" X 19' 1" ATTACHED 2-CAR GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 4/18/2022
- Issuing Office
- Current Status
- CofO Issued on 11/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2022 | GURUNATH NESARAJAH |
| Corrections Issued | 1/22/2022 | GURUNATH NESARAJAH |
| Plan Check Approved | 4/4/2022 | GURUNATH NESARAJAH |
| Issued | 4/18/2022 | APPLICANT |
| Building Plans Picked Up | 4/20/2022 | APPLICANT |
| CofO in Progress | 11/17/2022 | CHRIS CHRISTENSEN |
| CofO Issued | 11/29/2022 | JOHN JANSON |
| Permit Finaled | 11/29/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/16/2022 | AMIR KASHFI |
| Sewer availability | Cleared | 2/16/2022 | AMIR KASHFI |
| Eng Process Fee Ord 176,300 | Cleared | 2/17/2022 | AMIR KASHFI |
| ZA Case | Cleared | 4/6/2022 | DANG NGUYEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/16/2022 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 6/24/2022 | Not Ready for Inspection | JESUS PINEDA |
| Underground Mechanical | 7/1/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 7/7/2022 | Partial Approval | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 7/14/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Rough | 7/14/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 7/26/2022 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 7/26/2022 | Approved | CHRIS CHRISTENSEN |
| Shower Pan | 7/26/2022 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 8/8/2022 | Approved | CHRIS CHRISTENSEN |
| Wood Frame | 8/8/2022 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 9/2/2022 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 9/2/2022 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 9/2/2022 | Approved | CHRIS CHRISTENSEN |
| Insulation | 9/2/2022 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 9/2/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 9/9/2022 | Approved | JESUS PINEDA |
| Final | 10/26/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 10/26/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 10/26/2022 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Smoke Detectors | 10/26/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Final | 11/7/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Final | 11/7/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 11/7/2022 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Smoke Detectors | 11/7/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 11/16/2022 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 11/16/2022 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 11/16/2022 | SGSOV Approved | CHRIS CHRISTENSEN |
| Special/Order Compliance | 11/16/2022 | Partial Inspection | JESUS PINEDA |