16063 W DEVONSHIRE ST 91344
Certificate Information: 16063 W DEVONSHIRE ST 91344
- Application / Permit
- 21016-20000-56933
- Plan Check / Job No.
- B21VN16823
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT. PER GCS 65852.2 (e)(1)(A)
- Permit Issued
- Issued on 1/18/2022
- Issuing Office
- Current Status
- CofO Issued on 7/21/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/15/2021 | LUISANGEL VALENZUELA |
| Corrections Issued | 12/18/2021 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 1/13/2022 | ALFREDO JARA |
| Plan Check Approved | 1/14/2022 | ALFREDO JARA |
| Issued | 1/18/2022 | APPLICANT |
| Building Plans Picked Up | 1/26/2022 | APPLICANT |
| CofO in Progress | 7/21/2022 | JAVIER RAMOS JR |
| CofO Issued | 7/21/2022 | RONALD MYRICK |
| Permit Finaled | 7/21/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 12/22/2021 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 12/22/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/27/2021 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/4/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 3/4/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/4/2022 | Partial Approval | JENNIFER RABUCHIN |
| Underground Mechanical | 3/4/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/9/2022 | Partial Approval | MICHAEL TEMPLE |
| BUILDING-Rough-Frame | 4/4/2022 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 4/4/2022 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 4/4/2022 | Partial Approval | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 4/4/2022 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 4/4/2022 | Approved | JAVIER RAMOS JR |
| Insulation | 4/7/2022 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 4/12/2022 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 4/12/2022 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 4/12/2022 | Partial Approval | JAVIER RAMOS JR |
| Shower Pan | 4/12/2022 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 4/18/2022 | Approved | JAVIER RAMOS JR |
| Final | 5/18/2022 | Corrections Issued | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 5/18/2022 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 5/18/2022 | Approved | JAVIER RAMOS JR |
| Final | 5/24/2022 | Corrections Issued | JAVIER RAMOS JR |
| Final | 7/20/2022 | Conditional Approval | JAVIER RAMOS JR |