5261 N ROYER AVE 91367
Certificate Information: 5261 N ROYER AVE 91367
- Application / Permit
- 21016-20000-56658
- Plan Check / Job No.
- B21VN16789
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD IRR. 25'-5" x 28'-4" TO AND CONVERT (E) 25'-5" X 22'-1" DETACHED 2-CAR GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d). ALL WORK PER ENGINEER.
- Permit Issued
- Issued on 10/6/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 12/11/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 5/23/2022 | GURUNATH NESARAJAH |
| Plan Check Approved | 5/23/2022 | ANGELICA MARTINEZ |
| Building Plans Picked Up | 5/26/2022 | APPLICANT |
| Issued | 10/6/2023 | APPLICANT |
| CofO in Progress | 7/3/2024 | TROY SANDERS |
| Permit Finaled | 10/28/2024 | JOHN JANSON |
| CofO Issued | 10/28/2024 | JOHN JANSON |
| Permit Finaled | 10/28/2024 | JOHN JANSON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/19/2022 | RIDWAN HARDY |
| Address approval | Cleared | 4/29/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 4/29/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/2/2022 | MEGAN GODINEZ |
| Grading Pre-Inspection | Cleared | 5/6/2022 | KIRK LINKLATER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Fernandez,, Jose Carlos; Lic. No.: C76349 | 1838 E PRESTWICK AVE FRESNO, CA 93730 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/17/2023 | Partial Approval | TROY SANDERS |
| Excavation/Setback/Form/Re-Bar | 11/22/2023 | Approved | TROY SANDERS |
| Footing/Foundation/Slab | 11/22/2023 | Approved | TROY SANDERS |
| Deputy Wood Construction | 12/4/2023 | Conditional Approval | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2023 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 12/12/2023 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 12/12/2023 | Approved | TROY SANDERS |
| Green Building Rough | 12/12/2023 | Not Ready for Inspection | TROY SANDERS |
| HVAC-Rough | 12/12/2023 | Approved | TROY SANDERS |
| MERV13>=Rough | 12/12/2023 | Approved | TROY SANDERS |
| PLUMBING-Rough | 12/12/2023 | Approved | TROY SANDERS |
| Wood Frame | 12/12/2023 | Approved | TROY SANDERS |
| Green Building Rough | 12/19/2023 | Approved | TROY SANDERS |
| Insulation | 12/19/2023 | Approved | TROY SANDERS |
| Shower Pan | 12/19/2023 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 2/14/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Final | 2/14/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Green Building Final | 2/14/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| MERV13>=Final | 2/14/2024 | Approved | GEVORK IPCHYAN |
| SGSOV-Seismic Gas S/O Valve | 2/14/2024 | SGSOV Not Ready | GEVORK IPCHYAN |
| Smoke Detectors | 2/14/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Service/Power Release | 2/16/2024 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 6/4/2024 | SGSOV Not Ready | GEVORK IPCHYAN |
| Final | 7/3/2024 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 7/3/2024 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 7/3/2024 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 7/3/2024 | Approved | TROY SANDERS |
| Special/Order Compliance | 9/26/2024 | Corrections Issued | TROY SANDERS |