13353 3/4 W REEDLEY ST 91402
Certificate Information: 13353 3/4 W REEDLEY ST 91402
- Application / Permit
- 21016-20000-56632
- Plan Check / Job No.
- B21VN16779
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) RECREATION ROOM INTO (N) ACCESSORY DWELILNG UNIT PER GCS65852.2(e)(1)(A)
- Permit Issued
- Issued on 2/15/2022
- Issuing Office
- Current Status
- CofO Issued on 7/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2022 | NILOOFAR MEHRAIN |
| Corrections Issued | 1/18/2022 | NILOOFAR MEHRAIN |
| Quality Review Completed | 1/21/2022 | STEVEN KIM |
| Building Plans Picked Up | 1/28/2022 | APPLICANT |
| Plan Check Approved | 2/15/2022 | NILOOFAR MEHRAIN |
| Issued | 2/15/2022 | APPLICANT |
| CofO in Progress | 6/16/2023 | ROBERT GOLD |
| Permit Finaled | 7/6/2023 | MICHAEL SMITH |
| CofO Issued | 7/6/2023 | MICHAEL SMITH |
| Permit Finaled | 7/6/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| "T" removal | Cleared | 2/1/2022 | MIGUEL GAMBOA |
| Address approval | Cleared | 2/1/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 2/1/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 2/1/2022 | DAGOVERTO GUERRERO |
| Tract Map conditions | Cleared | 2/1/2022 | MIGUEL GAMBOA |
| ZA Case | Cleared | 2/1/2022 | MIGUEL GAMBOA |
| ZI | Cleared | 2/1/2022 | MIGUEL GAMBOA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2022 | No Access for Inspection | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2022 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Rough | 11/15/2022 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Rough | 11/15/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 11/15/2022 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 11/22/2022 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 11/22/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 11/22/2022 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 12/5/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Gas Test | 12/5/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Sewer | 12/5/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 12/16/2022 | Approved | GREGG CUMMINGS |
| Insulation | 12/27/2022 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 12/27/2022 | Partial Approval | GREGG CUMMINGS |
| Drywall Nailing | 1/6/2023 | Approved | GREGG CUMMINGS |
| Shower Pan | 1/13/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 1/18/2023 | Partial Approval | GREGG CUMMINGS |
| Final | 4/6/2023 | Corrections Issued | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 4/6/2023 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 4/6/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 6/9/2023 | Corrections Issued | GREGG CUMMINGS |
| Final | 6/15/2023 | OK to Issue CofO | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 6/15/2023 | SGSOV Approved | ROBERT GOLD |
| Smoke Detectors | 6/15/2023 | Approved | ROBERT GOLD |