16349 W TUDOR DR 91436

Certificate Information: 16349 W TUDOR DR 91436

Application / Permit
21016-20000-56568
Plan Check / Job No.
B21VN16741
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL TO THE (E) KITCHEN, NEW WINDOW OPENING IN THE (E) WALL, AND REMOVE A LOAD BEARING WALL TO BE REPLACED WITH A DROP BEAM. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 2/15/2022
Issuing Office
Current Status
Permit Finaled on 12/16/2022

Permit Application Status History

Submitted 12/3/2021 APPLICANT
Assigned to Plan Check Engineer 12/6/2021 COLIN LOREDO
Corrections Issued 12/6/2021 COLIN LOREDO
Plan Check Approved 2/3/2022 COLIN LOREDO
Building Plans Picked Up 2/9/2022 APPLICANT
Issued 2/15/2022 APPLICANT
Permit Finaled 12/15/2022 VINCENT HANLEY

Permit Application Clearance Information

Grading Pre-Inspection Cleared 12/27/2021 TIMOTHY POWELL

Contact Information

Contractor Owner-Builder       ,
Engineer Zhuang,, Wenbin; Lic. No.: S5236 205 S CHAPEL AVE #D-1      ALHAMBRA, CA 91801

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/6/2022 No Result Entered ROBERT VIERECK
Deputy Drilled-In Anchors 4/14/2022 Conditional Approval KRISTEN CAUSEY
Footing/Foundation/Slab 4/15/2022 Approved PETER FOLLING
Underground Mechanical 4/15/2022 Partial Approval PETER FOLLING
BUILDING-Rough-Frame 5/10/2022 Approved PETER FOLLING
ELECTRICAL-Rough 5/10/2022 Approved PETER FOLLING
PLUMBING-Rough 5/10/2022 Approved PETER FOLLING
Insulation 5/16/2022 Approved MORRIS JACKSON
Interior/Exterior Lathing 5/16/2022 Approved MORRIS JACKSON
Drywall Nailing 5/19/2022 Approved PETER FOLLING
Gas Test 5/19/2022 Approved PETER FOLLING
Final 12/15/2022 Permit Finaled VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 12/15/2022 SGSOV Approved VINCENT HANLEY
Smoke Detectors 12/15/2022 Approved VINCENT HANLEY