14405 W MIRANDA ST 91401

Certificate Information: 14405 W MIRANDA ST 91401

Application / Permit
21016-20000-56537
Plan Check / Job No.
B21VN16730
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMOVE 15' X 20' PORTION OF (E) STORAGE ATTACHED TO (E) GARAGE AND ADD 18'-10" X 22'-1" TO A CREATE A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 3/18/2022
Issuing Office
Current Status
CofO Issued on 3/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/3/2021 APPLICANT
Assigned to Plan Check Engineer 12/10/2021 RAPHAEL ROSAS
Corrections Issued 12/11/2021 RAPHAEL ROSAS
Applicant returned to address corrections 1/10/2022 RAPHAEL ROSAS
Plan Check Approved 3/13/2022 RAPHAEL ROSAS
Building Plans Picked Up 3/14/2022 APPLICANT
Issued 3/18/2022 APPLICANT
CofO in Progress 2/6/2023 RYAN SALAZAR
CofO in Progress 2/6/2023 ROBERT GOLD
Permit Finaled 3/3/2023 MICHAEL SMITH
CofO Issued 3/3/2023 MICHAEL SMITH
Permit Finaled 3/3/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/14/2021 AMIR KASHFI
Roof/Waste drainage to street Cleared 12/14/2021 AMIR KASHFI
Eng Process Fee Ord 176,300 Cleared 12/15/2021 AMIR KASHFI
Sewer availability Cleared 12/15/2021 AMIR KASHFI

Contact Information

Contractor Owner-Builder       ,
Engineer Mah,, Edwin Poy-Dor; Lic. No.: C27141 1740 APPIAN WAY      MONTEBELLO, CA 90640

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/11/2022 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 5/25/2022 Approved RICHARD DOCKUS
Gas Test 7/5/2022 Approved RICHARD DOCKUS
PLUMBING-Rough 7/5/2022 Approved RICHARD DOCKUS
Wood Frame 7/5/2022 Partial Approval RICHARD DOCKUS
ELECTRICAL-Rough 7/11/2022 Approved RICHARD DOCKUS
Wood Frame 7/13/2022 Partial Approval RICHARD DOCKUS
Interior/Exterior Lathing 7/15/2022 Not Ready for Inspection RICHARD DOCKUS
Insulation 7/19/2022 Approved RICHARD DOCKUS
Drywall Nailing 7/22/2022 Corrections Issued RICHARD DOCKUS
Shower Pan 8/2/2022 Approved RICHARD DOCKUS
Underground Mechanical 8/2/2022 Approved RICHARD DOCKUS
Interior/Exterior Lathing 8/5/2022 Partial Approval RICHARD DOCKUS
Drywall Nailing 8/11/2022 Approved RICHARD DOCKUS
Interior/Exterior Lathing 8/11/2022 Not Ready for Inspection RICHARD DOCKUS
Interior/Exterior Lathing 8/17/2022 Approved WILLIAM WREN
BUILDING-Rough-Frame 1/25/2023 Approved RYAN SALAZAR
Final 1/25/2023 Corrections Issued RYAN SALAZAR
Green Building Final 1/25/2023 Approved RYAN SALAZAR
Green Building Rough 1/25/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 1/25/2023 SGSOV Approved RYAN SALAZAR
Smoke Detectors 1/25/2023 Corrections Issued RYAN SALAZAR
Final 1/30/2023 OK to Issue CofO RYAN SALAZAR
Smoke Detectors 1/30/2023 Partial Approval RYAN SALAZAR
ELECTRICAL-Final 2/6/2023 Approved RYAN SALAZAR
Final 2/6/2023 OK to Issue CofO RYAN SALAZAR
HVAC-Final 2/6/2023 Approved RYAN SALAZAR
PLUMBING-Final 2/6/2023 Approved RYAN SALAZAR
Smoke Detectors 2/6/2023 Approved RYAN SALAZAR