14405 W MIRANDA ST 91401
Certificate Information: 14405 W MIRANDA ST 91401
- Application / Permit
- 21016-20000-56537
- Plan Check / Job No.
- B21VN16730
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- REMOVE 15' X 20' PORTION OF (E) STORAGE ATTACHED TO (E) GARAGE AND ADD 18'-10" X 22'-1" TO A CREATE A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 3/18/2022
- Issuing Office
- Current Status
- CofO Issued on 3/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2021 | RAPHAEL ROSAS |
| Corrections Issued | 12/11/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 1/10/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 3/13/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 3/14/2022 | APPLICANT |
| Issued | 3/18/2022 | APPLICANT |
| CofO in Progress | 2/6/2023 | RYAN SALAZAR |
| CofO in Progress | 2/6/2023 | ROBERT GOLD |
| Permit Finaled | 3/3/2023 | MICHAEL SMITH |
| CofO Issued | 3/3/2023 | MICHAEL SMITH |
| Permit Finaled | 3/3/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/14/2021 | AMIR KASHFI |
| Roof/Waste drainage to street | Cleared | 12/14/2021 | AMIR KASHFI |
| Eng Process Fee Ord 176,300 | Cleared | 12/15/2021 | AMIR KASHFI |
| Sewer availability | Cleared | 12/15/2021 | AMIR KASHFI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mah,, Edwin Poy-Dor; Lic. No.: C27141 | 1740 APPIAN WAY MONTEBELLO, CA 90640 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/11/2022 | Partial Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 5/25/2022 | Approved | RICHARD DOCKUS |
| Gas Test | 7/5/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 7/5/2022 | Approved | RICHARD DOCKUS |
| Wood Frame | 7/5/2022 | Partial Approval | RICHARD DOCKUS |
| ELECTRICAL-Rough | 7/11/2022 | Approved | RICHARD DOCKUS |
| Wood Frame | 7/13/2022 | Partial Approval | RICHARD DOCKUS |
| Interior/Exterior Lathing | 7/15/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Insulation | 7/19/2022 | Approved | RICHARD DOCKUS |
| Drywall Nailing | 7/22/2022 | Corrections Issued | RICHARD DOCKUS |
| Shower Pan | 8/2/2022 | Approved | RICHARD DOCKUS |
| Underground Mechanical | 8/2/2022 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 8/5/2022 | Partial Approval | RICHARD DOCKUS |
| Drywall Nailing | 8/11/2022 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 8/11/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Interior/Exterior Lathing | 8/17/2022 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 1/25/2023 | Approved | RYAN SALAZAR |
| Final | 1/25/2023 | Corrections Issued | RYAN SALAZAR |
| Green Building Final | 1/25/2023 | Approved | RYAN SALAZAR |
| Green Building Rough | 1/25/2023 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 1/25/2023 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 1/25/2023 | Corrections Issued | RYAN SALAZAR |
| Final | 1/30/2023 | OK to Issue CofO | RYAN SALAZAR |
| Smoke Detectors | 1/30/2023 | Partial Approval | RYAN SALAZAR |
| ELECTRICAL-Final | 2/6/2023 | Approved | RYAN SALAZAR |
| Final | 2/6/2023 | OK to Issue CofO | RYAN SALAZAR |
| HVAC-Final | 2/6/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 2/6/2023 | Approved | RYAN SALAZAR |
| Smoke Detectors | 2/6/2023 | Approved | RYAN SALAZAR |