8930 N STANWIN AVE 91331
Certificate Information: 8930 N STANWIN AVE 91331
- Application / Permit
- 21016-20000-56531
- Plan Check / Job No.
- B21VN16729
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 2-CAR GARAGE TO A DETACHED ADU PER STATE LAW (1-STORY)
- Permit Issued
- Issued on 1/13/2022
- Issuing Office
- Current Status
- CofO Issued on 11/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/14/2021 | CARLOS MONTES |
| Corrections Issued | 12/15/2021 | CARLOS MONTES |
| Plan Check Approved | 12/23/2021 | CARLOS MONTES |
| Issued | 1/13/2022 | APPLICANT |
| CofO in Progress | 11/3/2022 | GREGG CUMMINGS |
| CofO Issued | 11/12/2022 | MICHAEL SMITH |
| Permit Finaled | 11/12/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/22/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/22/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/22/2021 | CARLOS AGUILERA |
Contact Information
| No Data Available. |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/8/2022 | Conditional Approval | WILLIAM WREN |
| Footing/Foundation/Slab | 2/11/2022 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 2/11/2022 | Partial Approval | GREGG CUMMINGS |
| Sewer | 2/11/2022 | Corrections Issued | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 2/18/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Footing/Foundation/Slab | 2/18/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 2/24/2022 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 2/24/2022 | Approved | GREGG CUMMINGS |
| Sewer | 3/8/2022 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 3/16/2022 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 3/29/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 3/29/2022 | Approved | GREGG CUMMINGS |
| Green Building Rough | 3/29/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 3/29/2022 | Approved | GREGG CUMMINGS |
| Shower Pan | 3/29/2022 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 3/29/2022 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 4/5/2022 | Approved | GREGG CUMMINGS |
| Green Building Rough | 4/5/2022 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 4/5/2022 | Approved | GREGG CUMMINGS |
| Insulation | 4/5/2022 | Partial Approval | GREGG CUMMINGS |
| Insulation | 4/11/2022 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 4/11/2022 | Corrections Issued | WILLIAM WREN |
| Drywall Nailing | 4/21/2022 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 4/21/2022 | Approved | GREGG CUMMINGS |
| Final | 9/19/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 9/19/2022 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 9/19/2022 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 9/19/2022 | Approved | GREGG CUMMINGS |
| Final | 10/18/2022 | Corrections Issued | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 10/18/2022 | SGSOV Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 11/2/2022 | Approved | GREGG CUMMINGS |
| Final | 11/2/2022 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 11/2/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 11/2/2022 | Approved | GREGG CUMMINGS |