7921-7923 N MAYNARD AVE 91304

Certificate Information: 7921-7923 N MAYNARD AVE 91304

Application / Permit
21016-20000-56420
Plan Check / Job No.
B21VN16691
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT THE (E) (19'-3"x23'-7"), 453SQ.FT FT. ATTACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER CA GOVT. CODE 65852.2(e)(1)(A)
Permit Issued
Issued on 8/31/2022
Issuing Office
Valley
Current Status
CofO Issued on 5/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/8/2021 APPLICANT
Assigned to Plan Check Engineer 12/16/2021 PETER MOSESIAN
Corrections Issued 12/20/2021 PETER MOSESIAN
Building Plans Picked Up 12/22/2021 APPLICANT
Plan Check Approved 5/12/2022 PETER MOSESIAN
Issued 8/31/2022 APPLICANT
CofO in Progress 5/2/2023 CHRIS CHRISTENSEN
Permit Finaled 5/2/2023 JOHN JANSON
CofO Issued 5/2/2023 JOHN JANSON
Permit Finaled 5/2/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/22/2022 CARLOS AGUILERA
Sewer availability Cleared 3/22/2022 CARLOS AGUILERA
ZA Case Cleared 3/22/2022 MIGUEL GAMBOA
Eng Process Fee Ord 176,300 Cleared 3/23/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/7/2022 Approved SEAN WIRCH
Deputy Drilled-In Anchors 9/8/2022 Conditional Approval JESUS PINEDA
Footing/Foundation/Slab 9/8/2022 Approved TROY SANDERS
PLUMBING-Rough 9/8/2022 Partial Approval TROY SANDERS
Sewer 9/8/2022 Approved TROY SANDERS
BUILDING-Rough-Frame 9/22/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Rough 9/22/2022 Not Ready for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 10/12/2022 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 10/12/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 10/12/2022 Corrections Issued CHRIS CHRISTENSEN
BUILDING-Rough-Frame 10/18/2022 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 10/18/2022 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 10/18/2022 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 10/31/2022 Approved CHRIS CHRISTENSEN
Green Building Rough 10/31/2022 Approved CHRIS CHRISTENSEN
HVAC-Rough 10/31/2022 Approved CHRIS CHRISTENSEN
Insulation 10/31/2022 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 10/31/2022 Partial Approval CHRIS CHRISTENSEN
Drywall Nailing 11/14/2022 Approved JEFFREY PARD
Final 2/28/2023 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 2/28/2023 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 2/28/2023 SGSOV Not Ready CHRIS CHRISTENSEN
Smoke Detectors 2/28/2023 Approved CHRIS CHRISTENSEN
Final 3/14/2023 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 3/14/2023 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 3/14/2023 SGSOV Approved CHRIS CHRISTENSEN
Final 3/22/2023 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 3/22/2023 Approved CHRIS CHRISTENSEN