23204 W HAYNES ST 91307
Certificate Information: 23204 W HAYNES ST 91307
- Application / Permit
- 21016-20000-56224
- Plan Check / Job No.
- B21VN16626
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) 400 SF DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 1/5/2022
- Issuing Office
- Current Status
- CofO Issued on 4/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/8/2021 | JESSE ARELLANO |
| Corrections Issued | 12/10/2021 | JESSE ARELLANO |
| Issued | 1/5/2022 | APPLICANT |
| Building Plans Picked Up | 1/6/2022 | APPLICANT |
| CofO in Progress | 4/25/2023 | TROY SANDERS |
| Permit Finaled | 4/26/2023 | JOHN JANSON |
| CofO Issued | 4/26/2023 | JOHN JANSON |
| Permit Finaled | 4/26/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/11/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/11/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/14/2021 | CARLOS AGUILERA |
| Green Code | Cleared | 1/5/2022 | JESSE ARELLANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Singh,, Jasbir; Lic. No.: C38767 | 16194 EASTRIDGE CT CHINO HILLS, CA 91709 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/20/2022 | Partial Approval | TROY SANDERS |
| Sewer | 4/20/2022 | Approved | TROY SANDERS |
| Underground Mechanical | 4/20/2022 | Approved | TROY SANDERS |
| Footing/Foundation/Slab | 4/26/2022 | Corrections Issued | DAVID SCANTLIN |
| Wood Frame | 4/26/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 5/4/2022 | Approved | TROY SANDERS |
| PLUMBING-Rough | 5/4/2022 | Approved | TROY SANDERS |
| Shower Pan | 5/4/2022 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 5/10/2022 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 5/10/2022 | Not Ready for Inspection | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2022 | Partial Approval | TROY SANDERS |
| Green Building Rough | 5/10/2022 | Approved | TROY SANDERS |
| HVAC-Rough | 5/10/2022 | Approved | TROY SANDERS |
| Insulation | 5/10/2022 | Partial Approval | TROY SANDERS |
| Interior/Exterior Lathing | 5/10/2022 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 5/10/2022 | Approved | TROY SANDERS |
| Wood Frame | 5/10/2022 | Approved | TROY SANDERS |
| Insulation | 5/18/2022 | Approved | TROY SANDERS |
| Rough-Elec/Plmb/HVAC | 5/18/2022 | Approved | TROY SANDERS |
| Final | 7/27/2022 | Corrections Issued | DAVID SANDOVAL |
| Green Building Final | 7/27/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 7/27/2022 | SGSOV Not Ready | DAVID SANDOVAL |
| Smoke Detectors | 7/27/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Final | 8/3/2022 | Corrections Issued | TROY SANDERS |
| Green Building Final | 8/3/2022 | Not Ready for Inspection | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 8/3/2022 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 8/3/2022 | Approved | TROY SANDERS |
| Final | 4/25/2023 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 4/25/2023 | Approved | TROY SANDERS |