6574-6576 N CLEOMOORE AVE 91307
Certificate Information: 6574-6576 N CLEOMOORE AVE 91307
- Application / Permit
- 21016-20000-56065
- Plan Check / Job No.
- B21VN16500
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN CONVERT EXISTING ATTACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER ORDINANCE.
- Permit Issued
- Issued on 3/14/2022
- Issuing Office
- Current Status
- CofO Issued on 10/21/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/15/2021 | MICHAEL LOPEZ |
| Corrections Issued | 12/15/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 1/4/2022 | MICHAEL LOPEZ |
| Plan Check Approved | 3/11/2022 | MICHAEL LOPEZ |
| Issued | 3/14/2022 | APPLICANT |
| CofO in Progress | 9/29/2022 | TROY SANDERS |
| Permit Finaled | 10/21/2022 | JOHN JANSON |
| CofO Issued | 10/21/2022 | JOHN JANSON |
| Permit Finaled | 10/21/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/22/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 12/22/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/27/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/1/2022 | Approved | TROY SANDERS |
| PLUMBING-Rough | 4/1/2022 | Partial Approval | TROY SANDERS |
| Underground Mechanical | 4/1/2022 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 5/31/2022 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 5/31/2022 | Not Ready for Inspection | TROY SANDERS |
| Green Building Rough | 5/31/2022 | Not Ready for Inspection | TROY SANDERS |
| Insulation | 5/31/2022 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 5/31/2022 | Not Ready for Inspection | TROY SANDERS |
| BUILDING-Rough-Frame | 6/8/2022 | Approved | TROY SANDERS |
| Green Building Rough | 6/8/2022 | Not Ready for Inspection | TROY SANDERS |
| Rough-Elec/Plmb/HVAC | 6/8/2022 | Approved | TROY SANDERS |
| Green Building Rough | 6/14/2022 | Approved | TROY SANDERS |
| HVAC-Rough | 6/14/2022 | Approved | TROY SANDERS |
| Insulation | 6/14/2022 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 6/14/2022 | Partial Approval | TROY SANDERS |
| Underground Mechanical | 6/14/2022 | Partial Approval | TROY SANDERS |
| Drywall Nailing | 6/21/2022 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2022 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 6/24/2022 | Approved | JESUS PINEDA |
| Shower Pan | 6/24/2022 | Approved | JESUS PINEDA |
| Final | 9/19/2022 | Corrections Issued | TROY SANDERS |
| Green Building Final | 9/19/2022 | Not Ready for Inspection | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 9/19/2022 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 9/19/2022 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 9/28/2022 | Approved | TROY SANDERS |
| Final | 9/28/2022 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 9/28/2022 | Approved | TROY SANDERS |
| HVAC-Final | 9/28/2022 | Approved | TROY SANDERS |
| PLUMBING-Final | 9/28/2022 | Approved | TROY SANDERS |