14731 W RUNNYMEDE ST 91405

Certificate Information: 14731 W RUNNYMEDE ST 91405

Application / Permit
21016-20000-56016
Plan Check / Job No.
B21VN16466
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
DEMOLISH THE EXISTING PATIO COVER (20' x 21' = 420.00 s.f.) AND BUILD AN ADDITION TO THE MAIN HOUSE. (BEDROOM W / BATH AND CLOSET TO THE MAIN HOUSE
Permit Issued
Issued on 9/6/2022
Issuing Office
Valley
Current Status
CofO Issued on 2/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/29/2021 APPLICANT
Assigned to Plan Check Engineer 12/3/2021 JESSE ARELLANO
Corrections Issued 12/7/2021 JESSE ARELLANO
Applicant returned to address corrections 4/15/2022 JESSE ARELLANO
Applicant returned to address corrections 5/19/2022 JESSE ARELLANO
Building Plans Picked Up 5/25/2022 APPLICANT
Applicant returned to address corrections 8/29/2022 LAWRENCE QUIRANTE
Plan Check Approved 9/2/2022 ZAW HAN
Issued 9/6/2022 APPLICANT
CofO in Progress 1/17/2024 CHRISTOPHER ROJAS
Permit Finaled 2/27/2024 RUBEN SALAS
CofO Issued 2/27/2024 RUBEN SALAS
Permit Finaled 2/27/2024 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/10/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 3/23/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 3/23/2022 DAGOVERTO GUERRERO
Green Code Cleared 4/20/2022 JESSE ARELLANO

Contact Information

Contractor Owner-Builder       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVENUE      LONG BEACH, CA 90813

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/12/2022 Approved ALAN MORELOS
Deputy Drilled-In Anchors 9/27/2022 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 10/5/2022 Not Ready for Inspection WILLIAM WREN
PLUMBING-Rough 10/5/2022 Corrections Issued WILLIAM WREN
Footing/Foundation/Slab 10/17/2022 Not Ready for Inspection WILLIAM WREN
PLUMBING-Rough 10/17/2022 Partial Approval WILLIAM WREN
Excavation/Setback/Form/Re-Bar 10/24/2022 Corrections Issued GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 10/28/2022 Approved GREGG CUMMINGS
Footing/Foundation/Slab 10/28/2022 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 12/27/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Rough 12/27/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 1/12/2023 Partial Approval MATTHEW NELSON
Green Building Rough 1/12/2023 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 1/12/2023 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 4/25/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Green Building Rough 4/25/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Wood Frame 4/25/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 10/20/2023 Corrections Issued GREGG CUMMINGS
Green Building Rough 10/20/2023 Not Ready for Inspection GREGG CUMMINGS
Insulation 10/20/2023 Not Ready for Inspection GREGG CUMMINGS
Rough-Elec/Plmb/HVAC 10/20/2023 Not Ready for Inspection GREGG CUMMINGS
Wood Frame 10/20/2023 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 10/25/2023 Approved DAVID ANDERSON
ELECTRICAL-Rough 10/25/2023 Approved DAVID ANDERSON
Green Building Rough 10/25/2023 Approved DAVID ANDERSON
HVAC-Rough 10/25/2023 Approved DAVID ANDERSON
Insulation 11/17/2023 Approved JUAN VALENZUELA
Interior/Exterior Lathing 11/17/2023 Partial Approval JUAN VALENZUELA
Drywall Nailing 12/6/2023 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 12/6/2023 Approved CHRISTOPHER ROJAS
Final 1/16/2024 OK to Issue CofO CHRISTOPHER ROJAS
Green Building Final 1/16/2024 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 1/16/2024 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 1/16/2024 Approved CHRISTOPHER ROJAS