22720 W INGOMAR ST 91304
Certificate Information: 22720 W INGOMAR ST 91304
- Application / Permit
- 21016-20000-56004
- Plan Check / Job No.
- B21VN16458
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT THE (E) 23'-0" x 21'-0" ATTACHED GARAGE INTO A (N) BEDROOM AND BATHROOM. ADD 20'-6" x 20'-0" ATTACHED CARPORT. ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 2/7/2022
- Issuing Office
- Current Status
- CofO Issued on 4/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/3/2021 | JESSE ARELLANO |
| Corrections Issued | 12/4/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 1/12/2022 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 1/23/2022 | ZAW HAN |
| Plan Check Approved | 1/24/2022 | ZAW HAN |
| Building Plans Picked Up | 1/31/2022 | APPLICANT |
| Issued | 2/7/2022 | APPLICANT |
| CofO in Progress | 2/22/2024 | CHRIS CHRISTENSEN |
| Permit Finaled | 4/26/2024 | DANIEL ORRANTE |
| CofO Issued | 4/26/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/26/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/10/2021 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 12/13/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/16/2021 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/14/2022 | Partial Approval | JEFFREY PARD |
| PLUMBING-Rough | 2/14/2022 | Partial Approval | JEFFREY PARD |
| BUILDING-Rough-Frame | 3/9/2022 | Partial Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 3/9/2022 | Corrections Issued | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 3/9/2022 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 3/9/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Rough | 3/9/2022 | Approved | JOHNNY MIRANDA |
| Insulation | 3/21/2022 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 3/21/2022 | Partial Approval | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 4/5/2022 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 4/5/2022 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2022 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 4/5/2022 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 4/5/2022 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 4/18/2022 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 4/18/2022 | Approved | JUSTIN HAWLEY |
| Shower Pan | 4/18/2022 | Approved | JUSTIN HAWLEY |
| Final | 9/19/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 9/19/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 9/19/2022 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Smoke Detectors | 9/19/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Final | 1/3/2024 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 1/3/2024 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 1/3/2024 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 1/3/2024 | Approved | CHRIS CHRISTENSEN |
| Final | 2/21/2024 | OK to Issue CofO | CHRIS CHRISTENSEN |