7708 N WILKINSON AVE 91605
Certificate Information: 7708 N WILKINSON AVE 91605
- Application / Permit
- 21016-20000-55548
- Plan Check / Job No.
- B21VN16407
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) (20'-0"x18'-0"), 330 SQFT DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT W/NFPA 13D SPRINKLERS THROUGHOUT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 3/4/2022
- Issuing Office
- Current Status
- Issued on 3/4/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/29/2021 | PETER MOSESIAN |
| Corrections Issued | 11/29/2021 | PETER MOSESIAN |
| Building Plans Picked Up | 12/3/2021 | APPLICANT |
| Issued | 3/4/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/6/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/6/2021 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 12/6/2021 | JOSE DUARTE-DIAZ |
| Construction near power lines | Cleared | 2/15/2022 | TINA MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/15/2022 | Approved | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 1/11/2024 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 1/11/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2024 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 1/11/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 1/11/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 2/12/2024 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 5/22/2024 | Corrections Issued | MATTHEW NELSON |
| Insulation | 5/22/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Interior/Exterior Lathing | 5/22/2024 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 6/14/2024 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Rough | 6/18/2024 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 8/1/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 8/1/2024 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 8/1/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 8/1/2024 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 8/1/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 8/1/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 6/2/2025 | Approved | NICHOLAS TROWBRIDGE |