13522-13524 W DEBELL ST 91331

Certificate Information: 13522-13524 W DEBELL ST 91331

Application / Permit
21016-20000-55409
Plan Check / Job No.
B21VN16296
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 19'-2" X 23' ATTACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e). ALL WORK PER WFPP.
Permit Issued
Issued on 3/7/2022
Issuing Office
Current Status
CofO Issued on 9/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/24/2021 APPLICANT
Assigned to Plan Check Engineer 12/3/2021 RAPHAEL ROSAS
Corrections Issued 12/3/2021 RAPHAEL ROSAS
Applicant returned to address corrections 12/27/2021 RAPHAEL ROSAS
Applicant returned to address corrections 1/14/2022 RAPHAEL ROSAS
Plan Check Approved 2/22/2022 RAPHAEL ROSAS
Building Plans Picked Up 2/23/2022 APPLICANT
Issued 3/7/2022 APPLICANT
CofO in Progress 8/26/2022 GREGG CUMMINGS
CofO Issued 9/3/2022 MICHAEL SMITH
Permit Finaled 9/3/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/7/2021 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 12/7/2021 JOSE DUARTE-DIAZ
Sewer availability Cleared 12/7/2021 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/19/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Rough 5/19/2022 Partial Approval CHRISTOPHER DELLEFIELD
Sewer 5/19/2022 Approved CHRISTOPHER DELLEFIELD
Excavation/Setback/Form/Re-Bar 5/27/2022 Approved GREGG CUMMINGS
Footing/Foundation/Slab 5/27/2022 Approved GREGG CUMMINGS
ELECTRICAL-Rough 6/6/2022 Corrections Issued GREGG CUMMINGS
Wood Frame 6/6/2022 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Rough 6/13/2022 Approved GREGG CUMMINGS
PLUMBING-Rough 6/13/2022 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 6/16/2022 Approved GREGG CUMMINGS
Green Building Rough 6/16/2022 Approved GREGG CUMMINGS
HVAC-Rough 6/16/2022 Approved GREGG CUMMINGS
Insulation 6/27/2022 Approved WILLIAM WREN
Interior/Exterior Lathing 6/27/2022 Conditional Approval WILLIAM WREN
Drywall Nailing 7/1/2022 Approved GREGG CUMMINGS
Interior/Exterior Lathing 7/1/2022 Partial Approval GREGG CUMMINGS
Interior/Exterior Lathing 7/8/2022 Approved GREGG CUMMINGS
Shower Pan 7/8/2022 Approved GREGG CUMMINGS
ELECTRICAL-Final 8/18/2022 Not Ready for Inspection GREGG CUMMINGS
Final 8/18/2022 Corrections Issued GREGG CUMMINGS
Green Building Final 8/18/2022 Approved GREGG CUMMINGS
HVAC-Final 8/18/2022 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Final 8/18/2022 Not Ready for Inspection GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 8/18/2022 SGSOV Approved GREGG CUMMINGS
Smoke Detectors 8/18/2022 Approved GREGG CUMMINGS
ELECTRICAL-Final 8/26/2022 Approved GREGG CUMMINGS
Final 8/26/2022 OK to Issue CofO GREGG CUMMINGS
HVAC-Final 8/26/2022 Approved GREGG CUMMINGS
PLUMBING-Final 8/26/2022 Approved GREGG CUMMINGS