13522-13524 W DEBELL ST 91331
Certificate Information: 13522-13524 W DEBELL ST 91331
- Application / Permit
- 21016-20000-55409
- Plan Check / Job No.
- B21VN16296
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 19'-2" X 23' ATTACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e). ALL WORK PER WFPP.
- Permit Issued
- Issued on 3/7/2022
- Issuing Office
- Current Status
- CofO Issued on 9/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/3/2021 | RAPHAEL ROSAS |
| Corrections Issued | 12/3/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 12/27/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 1/14/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 2/22/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 2/23/2022 | APPLICANT |
| Issued | 3/7/2022 | APPLICANT |
| CofO in Progress | 8/26/2022 | GREGG CUMMINGS |
| CofO Issued | 9/3/2022 | MICHAEL SMITH |
| Permit Finaled | 9/3/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/7/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/7/2021 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 12/7/2021 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/19/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 5/19/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Sewer | 5/19/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Excavation/Setback/Form/Re-Bar | 5/27/2022 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 5/27/2022 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 6/6/2022 | Corrections Issued | GREGG CUMMINGS |
| Wood Frame | 6/6/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 6/13/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 6/13/2022 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 6/16/2022 | Approved | GREGG CUMMINGS |
| Green Building Rough | 6/16/2022 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 6/16/2022 | Approved | GREGG CUMMINGS |
| Insulation | 6/27/2022 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 6/27/2022 | Conditional Approval | WILLIAM WREN |
| Drywall Nailing | 7/1/2022 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 7/1/2022 | Partial Approval | GREGG CUMMINGS |
| Interior/Exterior Lathing | 7/8/2022 | Approved | GREGG CUMMINGS |
| Shower Pan | 7/8/2022 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 8/18/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 8/18/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 8/18/2022 | Approved | GREGG CUMMINGS |
| HVAC-Final | 8/18/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Final | 8/18/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 8/18/2022 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 8/18/2022 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 8/26/2022 | Approved | GREGG CUMMINGS |
| Final | 8/26/2022 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 8/26/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 8/26/2022 | Approved | GREGG CUMMINGS |