21522 W VENTURA BLVD 91364

Certificate Information: 21522 W VENTURA BLVD 91364

Application / Permit
21016-20000-55226
Plan Check / Job No.
B21VN16158
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(4) Gymnasium
Work Description
CHANGE OF USE FROM DANCE STUDIO TO A NEW FITNESS STUDIO. TENANT IMPROVEMENT TO INCLUDE DEMOLITION OF ALL FIRST FLOOR. ALL NEW MILLWORK AND FINISHES. NEW RESTROOMS AND REWORK OF EXISTING MECHANICAL AND ELECTRICAL (UNDER SEPARATE PERMIT)
Permit Issued
Issued on 5/12/2022
Issuing Office
Current Status
CofO Issued on 12/7/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/24/2021 APPLICANT
Assigned to Plan Check Engineer 11/24/2021 JOE VO
Corrections Issued 11/25/2021 JOE VO
Quality Review Completed 1/11/2022 LIPING TENG
Applicant returned to address corrections 4/26/2022 JOE VO
Plan Check Approved 5/2/2022 JOE VO
Issued 5/12/2022 APPLICANT
CofO in Progress 12/6/2022 ANDREW DORSO
Permit Finaled 12/7/2022 JEFFREY DURAN
CofO Issued 12/7/2022 JEFFREY DURAN
Permit Finaled 12/7/2022 JEFFREY DURAN

Permit Application Clearance Information

Specific Plan Cleared 1/3/2022 ERIN NASH
ZA Case Cleared 1/3/2022 ERIN NASH
"D" conditions Cleared 1/10/2022 MIGUEL GAMBOA
Sewer availability Cleared 1/14/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 1/25/2022 DAGOVERTO GUERRERO
DAS Clearance Cleared 3/10/2022 JOE VO
Fire Marshal Fire Life Safety Cleared 4/28/2022 ANDREW KO

Contact Information

Architect Neiss,, Scott Martin; Lic. No.: NA24089       ,
Contractor Pinhero Construction Inc; Lic. No.: 1009979-B       ,

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/6/2022 Approved DANIEL VARNUM
Footing/Foundation/Slab 6/6/2022 Approved DANIEL VARNUM
Verify Sprinkler Sign Off 6/16/2022 Not Ready for Inspection DANIEL VARNUM
Wood Frame 6/16/2022 Not Ready for Inspection DANIEL VARNUM
Drywall Nailing 6/29/2022 Partial Approval DANIEL VARNUM
Light Gage Steel Frame 6/29/2022 Partial Approval DANIEL VARNUM
Insulation 7/19/2022 Partial Approval KENNETH ROBERTS
Drywall Nailing 7/25/2022 Partial Approval CAMERON CHABAN
Drywall Nailing 8/24/2022 Approved CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 9/22/2022 SGSOV Not Ready ANDREW DORSO
Pre-Inspection 9/26/2022 Not Ready for Inspection CAMERON CHABAN
Final 11/30/2022 Corrections Issued ANDREW DORSO
SGSOV-Seismic Gas S/O Valve 11/30/2022 SGSOV Approved ANDREW DORSO
Smoke Detectors 11/30/2022 Approved ANDREW DORSO
Verify Sprinkler Sign Off 11/30/2022 Approved ANDREW DORSO
Wood Frame 11/30/2022 Approved ANDREW DORSO
Final 12/2/2022 Not Ready for Inspection RAFAEL CORTES
Final 12/6/2022 OK to Issue CofO ANDREW DORSO