10290 N LEV AVE 91331

Certificate Information: 10290 N LEV AVE 91331

Application / Permit
21016-20000-54878
Plan Check / Job No.
B21VN16009
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) 400 SQ. FT. GARAGE INTO A (N) ACCESSORY DWELLING UNIT GCS 65852.2(e)(1)(A). ALL WORK PER WFPP.
Permit Issued
Issued on 1/18/2022
Issuing Office
Current Status
CofO Issued on 4/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/18/2021 APPLICANT
Assigned to Plan Check Engineer 11/30/2021 PARISA ZAHABI
Corrections Issued 12/1/2021 PARISA ZAHABI
Plan Check Approved 1/11/2022 RICHARD GARCIA
Building Plans Picked Up 1/12/2022 APPLICANT
Issued 1/18/2022 APPLICANT
CofO in Progress 3/9/2023 JENNIFER RABUCHIN
Permit Finaled 4/5/2023 RONALD MYRICK
CofO Issued 4/5/2023 RONALD MYRICK
Permit Finaled 4/5/2023 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 12/2/2021 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 12/2/2021 JOSE DUARTE-DIAZ
Sewer availability Cleared 12/2/2021 JOSE DUARTE-DIAZ
ZI Cleared 12/6/2021 NELSON RODRIGUEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 7/27/2022 Not Ready for Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 7/27/2022 Approved JENNIFER RABUCHIN
Green Building Rough 7/27/2022 Not Ready for Inspection JENNIFER RABUCHIN
METHANE-Rough 7/27/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 8/12/2022 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 8/12/2022 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 8/12/2022 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 8/12/2022 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 9/23/2022 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 9/23/2022 Partial Approval MICHEL ABAJAN
Underground Mechanical 9/23/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 10/17/2022 Approved JENNIFER RABUCHIN
Green Building Rough 10/17/2022 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 10/17/2022 Approved JENNIFER RABUCHIN
PLUMBING-Rough 10/17/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 10/20/2022 Approved JENNIFER RABUCHIN
Green Building Rough 10/20/2022 Approved JENNIFER RABUCHIN
HVAC-Rough 10/20/2022 Approved JENNIFER RABUCHIN
Insulation 10/20/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 10/20/2022 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 11/4/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 11/4/2022 Approved JENNIFER RABUCHIN
Shower Pan 11/4/2022 Approved JENNIFER RABUCHIN
Drywall Nailing 11/17/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 3/8/2023 Approved JENNIFER RABUCHIN
Final 3/8/2023 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 3/8/2023 Approved JENNIFER RABUCHIN
HVAC-Final 3/8/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 3/8/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 3/8/2023 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 3/8/2023 Approved JENNIFER RABUCHIN