15948-15950 W DEVONSHIRE ST 91344
Certificate Information: 15948-15950 W DEVONSHIRE ST 91344
- Application / Permit
- 21016-20000-54865
- Plan Check / Job No.
- B21VN16001
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT 30' X 20' PORTION OF (E) SFD TO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A). ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 3/2/2022
- Issuing Office
- Current Status
- CofO Issued on 12/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/29/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 11/30/2021 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 2/1/2022 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 2/1/2022 | APPLICANT |
| Plan Check Approved | 2/15/2022 | GURUNATH NESARAJAH |
| Issued | 3/2/2022 | APPLICANT |
| CofO in Progress | 12/19/2022 | JAVIER RAMOS JR |
| CofO in Progress | 12/19/2022 | ROBERT GOLD |
| CofO Issued | 12/20/2022 | MICHAEL SMITH |
| Permit Finaled | 12/20/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/7/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/12/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/12/2022 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 1/21/2022 | ALEXANDER ANDREWS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Van, Elden, Alexander Craig; Lic. No.: C71696 | 2415 FORDHAM DR COSTA MESA, CA 92626 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/6/2022 | Corrections Issued | JAVIER RAMOS JR |
| Pre-Inspection | 4/6/2022 | Partial Inspection | JAVIER RAMOS JR |
| Sewer | 4/6/2022 | Approved | JAVIER RAMOS JR |
| Deputy Drilled-In Anchors | 4/14/2022 | Conditional Approval | MICHAEL TEMPLE |
| Excavation/Setback/Form/Re-Bar | 4/18/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| PLUMBING-Rough | 4/18/2022 | Partial Approval | JAVIER RAMOS JR |
| Reinforced Concrete Frame | 4/18/2022 | Partial Inspection | JAVIER RAMOS JR |
| Sewer | 4/18/2022 | Partial Inspection | JAVIER RAMOS JR |
| Wood Frame | 4/18/2022 | Partial Inspection | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 4/27/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 4/27/2022 | Corrections Issued | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 4/27/2022 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 4/27/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| PLUMBING-Rough | 4/27/2022 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 5/5/2022 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 5/5/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Rough | 5/5/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 5/10/2022 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 5/10/2022 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 5/10/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 5/13/2022 | Partial Approval | JAVIER RAMOS JR |
| Green Building Rough | 5/13/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Rough | 5/13/2022 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 6/1/2022 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 6/1/2022 | Approved | JAVIER RAMOS JR |
| Insulation | 6/1/2022 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 6/1/2022 | Partial Approval | JAVIER RAMOS JR |
| Drywall Nailing | 6/9/2022 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 7/12/2022 | Corrections Issued | DEANDRE HOFFMAN |
| Final | 11/4/2022 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 11/4/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 11/4/2022 | SGSOV Not Required | JAVIER RAMOS JR |
| Smoke Detectors | 11/4/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Final | 11/16/2022 | Partial Approval | JAVIER RAMOS JR |
| Green Building Final | 11/16/2022 | Approved | JAVIER RAMOS JR |
| Smoke Detectors | 11/16/2022 | Approved | JAVIER RAMOS JR |
| Final | 12/6/2022 | OK to Issue CofO | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 12/6/2022 | SGSOV Approved | JAVIER RAMOS JR |
| Service/Power Release | 12/6/2022 | Approved | JAVIER RAMOS JR |