2431 S CATALINA ST 90007
Certificate Information: 2431 S CATALINA ST 90007
- Application / Permit
- 21016-20000-54729
- Plan Check / Job No.
- B21VN15944
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20' X 22' DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 6/7/2022
- Issuing Office
- Current Status
- Issued on 6/7/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/17/2021 | RAPHAEL ROSAS |
| Corrections Issued | 12/18/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 5/5/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 5/21/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 5/26/2022 | APPLICANT |
| Issued | 6/7/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/28/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 12/28/2021 | CELINA MORENO |
| Sewer availability | Cleared | 12/28/2021 | CELINA MORENO |
| HPOZ | Cleared | 4/10/2022 | LYDIA CHAPMAN |
| ZI | Cleared | 4/10/2022 | LYDIA CHAPMAN |
Contact Information
| Contractor | R L Remodeling Inc; Lic. No.: 885032-B | 22817 VENTURA BLVD #852 WOODLAND HILLS, CA 91364 |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 8916 LONGDON AVE #C TEMPLE CITY, CA 91780 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/10/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 6/14/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 6/17/2022 | Partial Inspection | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 6/27/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| Underground Mechanical | 6/27/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 8/31/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 9/7/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 9/14/2022 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 11/7/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 11/7/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| Green Building Rough | 11/7/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| HVAC-Rough | 11/7/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| METHANE-Rough | 11/7/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 11/23/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 11/23/2022 | Approved | KATHRYN BUTTERWORTH |
| Green Building Rough | 11/23/2022 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Rough | 11/23/2022 | Approved | KATHRYN BUTTERWORTH |
| METHANE-Rough | 11/23/2022 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 11/23/2022 | Approved | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| Insulation | 12/1/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 12/1/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Shower Pan | 12/1/2022 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 12/6/2022 | Approved | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Insulation | 12/6/2022 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 12/6/2022 | Approved | KATHRYN BUTTERWORTH |
| Shower Pan | 12/6/2022 | Approved | KATHRYN BUTTERWORTH |
| Drywall Nailing | 12/12/2022 | No Access for Inspection | KATHRYN BUTTERWORTH |
| Drywall Nailing | 12/14/2022 | Approved | ALIZAH MAYAGOITIA |
| Final | 2/21/2023 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 2/21/2023 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 2/21/2023 | SGSOV Not Ready | STUART CHAPMAN |
| Smoke Detectors | 2/21/2023 | Approved | STUART CHAPMAN |
| Final | 2/27/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 2/27/2023 | SGSOV Approved | KATHRYN BUTTERWORTH |
| Final | 3/6/2023 | No Access for Inspection | KATHRYN BUTTERWORTH |
| Final | 3/15/2023 | Corrections Issued | KATHRYN BUTTERWORTH |