6943-6945 N NAGLE AVE 91605
Certificate Information: 6943-6945 N NAGLE AVE 91605
- Application / Permit
- 21016-20000-54672
- Plan Check / Job No.
- B21VN15906
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT (362 SQ FT) PER GCS 65852.2(e)(1)(A) and 65852.22
- Permit Issued
- Issued on 1/6/2022
- Issuing Office
- Current Status
- CofO Issued on 12/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/29/2021 | JESSE ARELLANO |
| Corrections Issued | 11/29/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 12/9/2021 | JESSE ARELLANO |
| Plan Check Approved | 1/5/2022 | JEROME MAGAT PALMA |
| Issued | 1/6/2022 | APPLICANT |
| Building Plans Picked Up | 1/7/2022 | APPLICANT |
| CofO in Progress | 10/3/2022 | RAFAEL CORTES |
| No Progress | 10/4/2022 | MICHAEL SMITH |
| CofO in Progress | 10/4/2022 | RAFAEL CORTES |
| CofO in Progress | 12/7/2022 | ARAM AVEDISIAN |
| Permit Finaled | 12/24/2022 | MICHAEL SMITH |
| CofO Issued | 12/24/2022 | MICHAEL SMITH |
| Permit Finaled | 12/24/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 11/30/2021 | AMIR KASHFI |
| Sewer availability | Cleared | 11/30/2021 | AMIR KASHFI |
| Eng Process Fee Ord 176,300 | Cleared | 12/2/2021 | AMIR KASHFI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/28/2022 | Conditional Approval | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 4/28/2022 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 5/18/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| HVAC-Rough | 5/18/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 5/18/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Wood Frame | 5/18/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 5/24/2022 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 5/24/2022 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 5/24/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 5/24/2022 | Approved | CHRISTOPHE COCHRAN |
| Wood Frame | 5/24/2022 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 5/27/2022 | Partial Approval | MISAEL ESPARZA |
| Drywall Nailing | 6/6/2022 | Approved | CHRISTOPHE COCHRAN |
| Sewer | 8/19/2022 | Approved | ALAN MORELOS |
| Underground Mechanical | 8/19/2022 | Approved | ALAN MORELOS |
| BUILDING-Rough-Frame | 9/30/2022 | Approved | RAFAEL CORTES |
| ELECTRICAL-Final | 9/30/2022 | Approved | RAFAEL CORTES |
| Final | 9/30/2022 | Corrections Issued | RAFAEL CORTES |
| Green Building Final | 9/30/2022 | Approved | RAFAEL CORTES |
| Green Building Rough | 9/30/2022 | Approved | RAFAEL CORTES |
| HVAC-Final | 9/30/2022 | Approved | RAFAEL CORTES |
| PLUMBING-Final | 9/30/2022 | Approved | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 9/30/2022 | SGSOV Approved | RAFAEL CORTES |
| Service/Power Release | 9/30/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Smoke Detectors | 9/30/2022 | Approved | RAFAEL CORTES |
| Final | 10/4/2022 | Corrections Issued | RAFAEL CORTES |
| Final | 11/23/2022 | Corrections Issued | ARAM AVEDISIAN |
| Service/Power Release | 11/23/2022 | Not Ready for Inspection | ARAM AVEDISIAN |
| Final | 12/7/2022 | OK to Issue CofO | ARAM AVEDISIAN |
| Service/Power Release | 12/7/2022 | Approved | ARAM AVEDISIAN |