12335 W ALLIN ST 90230
Certificate Information: 12335 W ALLIN ST 90230
- Application / Permit
- 21016-20000-54534
- Plan Check / Job No.
- B21VN15803
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION FROM DETACHED (E) 400 SQ. FT. REC. ROOM INTO A (N) DETACHED ACCESSORY DWELLING UNIT TO COMPLY WITH GCS 65852.2(e)(1)(A). ALL WORK PER WFPP
- Permit Issued
- Issued on 8/9/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/15/2021 | ALFRED RAMIREZ |
| Corrections Issued | 12/15/2021 | ALFRED RAMIREZ |
| Plan Check Approved | 5/12/2022 | ALFRED RAMIREZ |
| Building Plans Picked Up | 7/27/2022 | APPLICANT |
| Issued | 8/9/2022 | APPLICANT |
| CofO in Progress | 4/26/2023 | JESUS RODRIGUEZ |
| Permit Finaled | 4/26/2023 | DANIEL ORRANTE |
| CofO Issued | 4/26/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/26/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/29/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 4/29/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/2/2022 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 8/18/2022 | No Access for Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 8/22/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Green Building Rough | 8/22/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 8/25/2022 | Corrections Issued | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 10/3/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 10/3/2022 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 10/3/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Rough | 10/3/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 10/3/2022 | Approved | JESUS RODRIGUEZ |
| Wood Frame | 10/3/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 10/28/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 10/28/2022 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 10/28/2022 | SGSOV Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 11/22/2022 | Approved | JESUS RODRIGUEZ |
| Insulation | 11/22/2022 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 11/28/2022 | Approved | HERBERT GIRON |
| Green Building Rough | 11/28/2022 | Approved | HERBERT GIRON |
| Shower Pan | 12/21/2022 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Final | 12/29/2022 | Corrections Issued | CLAYTON GRAHAM |
| Shower Pan | 12/29/2022 | Approved | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2023 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 4/3/2023 | Approved | JESUS RODRIGUEZ |
| Final | 4/3/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 4/3/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Smoke Detectors | 4/3/2023 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 4/25/2023 | Approved | JESUS RODRIGUEZ |
| Final | 4/25/2023 | OK to Issue CofO | JESUS RODRIGUEZ |
| Green Building Final | 4/25/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 4/25/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 4/25/2023 | Approved | JESUS RODRIGUEZ |
| Service/Power Release | 4/25/2023 | Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 4/25/2023 | Approved | JESUS RODRIGUEZ |