12020 W ALLIN ST 90230
Certificate Information: 12020 W ALLIN ST 90230
- Application / Permit
- 21016-20000-54480
- Plan Check / Job No.
- B21VN15773
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) 19'-0" X 20'-10" (360 SF) REC. ROOM INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK PER WFPP.
- Permit Issued
- Issued on 12/15/2021
- Issuing Office
- Current Status
- CofO Issued on 1/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/17/2021 | OMAR GARNICA |
| Corrections Issued | 11/18/2021 | OMAR GARNICA |
| Plan Check Approved | 12/15/2021 | OMAR GARNICA |
| Issued | 12/15/2021 | APPLICANT |
| Building Plans Picked Up | 2/8/2022 | APPLICANT |
| CofO in Progress | 12/27/2022 | JESUS RODRIGUEZ |
| Permit Finaled | 1/3/2023 | DANIEL ORRANTE |
| CofO Issued | 1/3/2023 | DANIEL ORRANTE |
| Permit Finaled | 1/3/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 11/23/2021 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 11/23/2021 | SAUL GARCIA |
| Sewer availability | Cleared | 11/23/2021 | SAUL GARCIA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/14/2022 | Partial Approval | STEPHANIE SWANSON |
| Deputy Drilled-In Anchors | 3/23/2022 | Conditional Approval | RICHARD STEINBACH |
| PLUMBING-Rough | 4/28/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 7/13/2022 | Not Ready for Inspection | PATRICK QUALEY |
| Pre-Inspection | 7/13/2022 | Corrections Issued | PATRICK QUALEY |
| ELECTRICAL-Rough | 8/19/2022 | Not Ready for Inspection | CLAYTON GRAHAM |
| HVAC-Rough | 8/19/2022 | Corrections Issued | CLAYTON GRAHAM |
| PLUMBING-Rough | 8/19/2022 | Approved | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 8/24/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 9/29/2022 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 9/29/2022 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 9/29/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 9/29/2022 | Approved | JESUS RODRIGUEZ |
| Insulation | 9/29/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 9/29/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 9/29/2022 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 10/12/2022 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 10/12/2022 | Approved | JESUS RODRIGUEZ |
| Service/Power Release | 10/12/2022 | Partial Inspection | JESUS RODRIGUEZ |
| Shower Pan | 10/12/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Shower Pan | 10/14/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Shower Pan | 10/27/2022 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 12/9/2022 | SGSOV Not Ready | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 12/19/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Final | 12/19/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 12/19/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 12/19/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 12/19/2022 | Corrections Issued | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 12/19/2022 | SGSOV Not Ready | JESUS RODRIGUEZ |
| Smoke Detectors | 12/19/2022 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 12/27/2022 | Approved | JESUS RODRIGUEZ |
| Final | 12/27/2022 | OK to Issue CofO | JESUS RODRIGUEZ |
| HVAC-Final | 12/27/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 12/27/2022 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 12/27/2022 | SGSOV Approved | JESUS RODRIGUEZ |
| Special/Order Compliance | 12/27/2022 | Partial Inspection | CLAYTON GRAHAM |