12020 W ALLIN ST 90230

Certificate Information: 12020 W ALLIN ST 90230

Application / Permit
21016-20000-54480
Plan Check / Job No.
B21VN15773
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) 19'-0" X 20'-10" (360 SF) REC. ROOM INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK PER WFPP.
Permit Issued
Issued on 12/15/2021
Issuing Office
Current Status
CofO Issued on 1/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/16/2021 APPLICANT
Assigned to Plan Check Engineer 11/17/2021 OMAR GARNICA
Corrections Issued 11/18/2021 OMAR GARNICA
Plan Check Approved 12/15/2021 OMAR GARNICA
Issued 12/15/2021 APPLICANT
Building Plans Picked Up 2/8/2022 APPLICANT
CofO in Progress 12/27/2022 JESUS RODRIGUEZ
Permit Finaled 1/3/2023 DANIEL ORRANTE
CofO Issued 1/3/2023 DANIEL ORRANTE
Permit Finaled 1/3/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 11/23/2021 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 11/23/2021 SAUL GARCIA
Sewer availability Cleared 11/23/2021 SAUL GARCIA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/14/2022 Partial Approval STEPHANIE SWANSON
Deputy Drilled-In Anchors 3/23/2022 Conditional Approval RICHARD STEINBACH
PLUMBING-Rough 4/28/2022 Not Ready for Inspection JESUS RODRIGUEZ
BUILDING-Rough-Frame 7/13/2022 Not Ready for Inspection PATRICK QUALEY
Pre-Inspection 7/13/2022 Corrections Issued PATRICK QUALEY
ELECTRICAL-Rough 8/19/2022 Not Ready for Inspection CLAYTON GRAHAM
HVAC-Rough 8/19/2022 Corrections Issued CLAYTON GRAHAM
PLUMBING-Rough 8/19/2022 Approved CLAYTON GRAHAM
ELECTRICAL-Rough 8/24/2022 Not Ready for Inspection JESUS RODRIGUEZ
BUILDING-Rough-Frame 9/29/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 9/29/2022 Approved JESUS RODRIGUEZ
Green Building Rough 9/29/2022 Approved JESUS RODRIGUEZ
HVAC-Rough 9/29/2022 Approved JESUS RODRIGUEZ
Insulation 9/29/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 9/29/2022 Approved JESUS RODRIGUEZ
PLUMBING-Rough 9/29/2022 Approved JESUS RODRIGUEZ
Drywall Nailing 10/12/2022 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 10/12/2022 Approved JESUS RODRIGUEZ
Service/Power Release 10/12/2022 Partial Inspection JESUS RODRIGUEZ
Shower Pan 10/12/2022 Not Ready for Inspection JESUS RODRIGUEZ
Shower Pan 10/14/2022 Corrections Issued JESUS RODRIGUEZ
Shower Pan 10/27/2022 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 12/9/2022 SGSOV Not Ready JESUS RODRIGUEZ
ELECTRICAL-Final 12/19/2022 Corrections Issued JESUS RODRIGUEZ
Final 12/19/2022 Corrections Issued JESUS RODRIGUEZ
Green Building Final 12/19/2022 Approved JESUS RODRIGUEZ
HVAC-Final 12/19/2022 Approved JESUS RODRIGUEZ
PLUMBING-Final 12/19/2022 Corrections Issued JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 12/19/2022 SGSOV Not Ready JESUS RODRIGUEZ
Smoke Detectors 12/19/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 12/27/2022 Approved JESUS RODRIGUEZ
Final 12/27/2022 OK to Issue CofO JESUS RODRIGUEZ
HVAC-Final 12/27/2022 Approved JESUS RODRIGUEZ
PLUMBING-Final 12/27/2022 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 12/27/2022 SGSOV Approved JESUS RODRIGUEZ
Special/Order Compliance 12/27/2022 Partial Inspection CLAYTON GRAHAM