12928 W VENICE BLVD 90066
Certificate Information: 12928 W VENICE BLVD 90066
- Application / Permit
- 21016-20000-54437
- Plan Check / Job No.
- B21VN15752
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Grocery Store
- Work Description
- CHANGE OF USE FROM RETAIL TO GROCERY STORE.
- Permit Issued
- Issued on 2/3/2022
- Issuing Office
- Current Status
- CofO Issued on 7/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2021 | RAPHAEL ROSAS |
| Corrections Issued | 11/26/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 12/26/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 1/28/2022 | APPLICANT |
| Issued | 2/3/2022 | APPLICANT |
| CofO in Progress | 7/25/2022 | GRANT WOODS |
| Permit Finaled | 7/25/2022 | DAVID TSAU |
| Permit Finaled | 7/25/2022 | DAVID TSAU |
| CofO Issued | 7/25/2022 | DAVID TSAU |
Permit Application Clearance Information
| Sewer availability | Cleared | 12/6/2021 | DINAH GARIN |
| "Q" conditions | Cleared | 12/7/2021 | STEVEN WECHSLER |
| Eng Process Fee Ord 176,300 | Cleared | 12/8/2021 | DINAH GARIN |
| Miscellaneous | Cleared | 12/9/2021 | RAYMOND MUGAMBWA |
| Miscellaneous | Cleared | 12/9/2021 | RAYMOND MUGAMBWA |
| Specific Plan | Cleared | 1/12/2022 | EDUARDO HERMOSO |
Contact Information
| Contractor | Priceless Construction And Painting Inc; Lic. No.: 930116-B | 405 N KEYSTONE ST BURBANK, CA 91506 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/1/2022 | No Access for Inspection | JOHN DODGE |
| Pre-Inspection | 3/9/2022 | Approved | GRANT WOODS |
| Footing/Foundation/Slab | 3/11/2022 | Conditional Approval | ALAN NOVAK |
| Deputy Drilled-In Anchors | 3/22/2022 | Conditional Approval | GRANT WOODS |
| Wood Frame | 5/10/2022 | Approved | PAUL DAVIDSON |
| Drywall Nailing | 5/13/2022 | Approved | NICK LAROCCA |
| Insulation | 5/13/2022 | Approved | NICK LAROCCA |
| Pre-Inspection | 6/7/2022 | Partial Inspection | SORIN CIRSTOIU |
| Final | 6/28/2022 | Not Ready for Inspection | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 6/28/2022 | SGSOV Not Ready | SORIN CIRSTOIU |
| Smoke Detectors | 6/28/2022 | Not Ready for Inspection | SORIN CIRSTOIU |
| Final | 7/8/2022 | Not Ready for Inspection | ALAN NOVAK |
| SGSOV-Seismic Gas S/O Valve | 7/8/2022 | SGSOV Approved | ALAN NOVAK |
| Smoke Detectors | 7/8/2022 | Approved | ALAN NOVAK |
| Final | 7/19/2022 | Not Ready for Inspection | GRANT WOODS |
| Final | 7/22/2022 | OK to Issue CofO | GRANT WOODS |