3449 N OAK GLEN DR 90068

Certificate Information: 3449 N OAK GLEN DR 90068

Application / Permit
21016-20000-54261
Plan Check / Job No.
B21VN15700
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ECPC: FOUNDATION UNDERPIN USING GRADE BEAM AND PILES TO (E) SFD, ALL WORK PER EGINEERING.
Permit Issued
Issued on 6/27/2022
Issuing Office
Metro
Current Status
Permit Finaled on 2/14/2023

Permit Application Status History

Submitted 11/17/2021 APPLICANT
Assigned to Plan Check Engineer 11/18/2021 LUISANGEL VALENZUELA
Corrections Issued 11/19/2021 LUISANGEL VALENZUELA
Applicant returned to address corrections 3/25/2022 LUISANGEL VALENZUELA
Plan Check Approved 4/7/2022 LUISANGEL VALENZUELA
Building Plans Picked Up 4/8/2022 APPLICANT
Issued 6/27/2022 APPLICANT
Permit Finaled 2/13/2023 BRIAN SULLIVAN

Permit Application Clearance Information

ZI Cleared 12/6/2021 MIGUEL GAMBOA
Grading Pre-Inspection Cleared 3/29/2022 LUISANGEL VALENZUELA

Contact Information

Contractor Alpha Structural Inc; Lic. No.: 663409-B 8334 FOOTHILL BLVD      SUNLAND, CA 91040
Engineer Demers,, Joe Alan; Lic. No.: C71535 894 SANTA MARIA CIRCLE      DUARTE, CA 91010
Engineer Su,, Yu-Ting; Lic. No.: C76714 28 SAGE      LAKE FOREST, CA 92630
Geologist Carrle,, Conrad Henry; Lic. No.: EG2359 23128 WILDWOOD ROAD      NEWHALL, CA 91321

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 9/2/2022 Conditional Approval CLAYTON GRAHAM
Pre-Inspection 9/9/2022 Approved BRIAN SULLIVAN
Footing/Foundation/Slab 9/15/2022 Corrections Issued BRIAN SULLIVAN
Deputy Drilled-In Anchors 9/16/2022 Conditional Approval BRIAN SULLIVAN
Footing/Foundation/Slab 9/19/2022 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 9/28/2022 Approved BRIAN SULLIVAN
Final 12/8/2022 No Access for Inspection BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 12/8/2022 SGSOV Not Ready BRIAN SULLIVAN
Smoke Detectors 12/8/2022 No Access for Inspection BRIAN SULLIVAN
Final 2/13/2023 Permit Finaled BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 2/13/2023 SGSOV Approved BRIAN SULLIVAN
Smoke Detectors 2/13/2023 Approved BRIAN SULLIVAN