10524 N WOODLEY AVE 91344

Certificate Information: 10524 N WOODLEY AVE 91344

Application / Permit
21016-20000-53579
Plan Check / Job No.
B21VN15676
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) 420 SQ. FT. GARAGE INTO AN ACCESSORY DWELLING UNIT PER GCS 65852.2. ALL WORK SHALL CONFORM TO THE WFPP.
Permit Issued
Issued on 3/8/2022
Issuing Office
Current Status
Issued on 3/8/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/14/2021 APPLICANT
Assigned to Plan Check Engineer 12/22/2021 COLIN LOREDO
Corrections Issued 12/27/2021 COLIN LOREDO
Building Plans Picked Up 12/28/2021 APPLICANT
Plan Check Approved 3/4/2022 COLIN LOREDO
Issued 3/8/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/4/2022 AMIR KASHFI
Sewer availability Cleared 1/4/2022 AMIR KASHFI
Eng Process Fee Ord 176,300 Cleared 1/5/2022 AMIR KASHFI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/26/2022 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 1/30/2023 Corrections Issued JOHN COLEMAN
Excavation/Setback/Form/Re-Bar 1/31/2023 Approved JOHN COLEMAN
Footing/Foundation/Slab 1/31/2023 Approved JOHN COLEMAN
Footing/Foundation/Slab 2/6/2023 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 2/6/2023 Partial Approval JAVIER RAMOS JR
Pre-Inspection 2/6/2023 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 2/27/2023 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 4/29/2024 Partial Inspection JAVIER RAMOS JR
Pre-Inspection 4/29/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 6/11/2024 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 6/11/2024 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 7/15/2024 No Access for Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 7/17/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 7/17/2024 Approved MICHEL ABAJAN
HVAC-Rough 6/4/2025 Corrections Issued CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 7/14/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 7/14/2025 Approved CHRISTOPHER ROJAS
HVAC-Rough 7/14/2025 Approved CHRISTOPHER ROJAS
Insulation 8/4/2025 Approved CHRISTOPHER ROJAS
Drywall Nailing 8/14/2025 Approved CHRISTOPHER ROJAS