Work Description
ADDITION TO DETACHED GARAGE AND CONVERT TO AN ADU.
Permit Issued
Issued on 3/31/2022
Issuing Office
Current Status
Issued on 3/31/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/15/2021 APPLICANT
Assigned to Plan Check Engineer 11/16/2021 JOE VO
Corrections Issued 11/17/2021 JOE VO
Assigned to Plan Check Engineer 11/18/2021 JOE VO
Corrections Issued 1/12/2022 JOE VO
Plan Check Approved 3/12/2022 JOE VO
Issued 3/31/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/1/2021 JEANETTE VONG
Hydrant and Access approval Cleared 2/23/2022 JOHN CONNEALLY
Low Impact Development Cleared 3/9/2022 CHRIS VONG
Eng Process Fee Ord 176,300 Cleared 3/11/2022 JEANETTE VONG
Roof/Waste drainage to street Cleared 3/11/2022 JEANETTE VONG
Sewer availability Cleared 3/11/2022 JEANETTE VONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/14/2022 Partial Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 6/21/2022 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 8/24/2022 Approved JOAQUIN GREENOUGH
ELECTRICAL-Rough 8/24/2022 Approved JOAQUIN GREENOUGH
Gas Test 8/24/2022 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 8/24/2022 Approved JOAQUIN GREENOUGH
Insulation 9/1/2022 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 9/1/2022 Approved ENRIQUE MIRELES
Shower Pan 9/1/2022 Approved ENRIQUE MIRELES
Drywall Nailing 9/6/2022 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 9/6/2022 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 9/6/2022 Partial Approval ALEJANDRO DE ARTOLA
Final 11/23/2022 Corrections Issued JULIAN AMAYA
SGSOV-Seismic Gas S/O Valve 11/23/2022 SGSOV Approved JULIAN AMAYA
Smoke Detectors 11/23/2022 Approved JULIAN AMAYA
Final 12/15/2022 Conditional Approval BRENDAN MORELLI
Final 1/25/2023 Corrections Issued BRENDAN MORELLI
Final 2/8/2023 Corrections Issued BRENDAN MORELLI