10418 1/2 N TELFAIR AVE 91331
Certificate Information: 10418 1/2 N TELFAIR AVE 91331
- Application / Permit
- 21016-20000-53246
- Plan Check / Job No.
- B21VN15631
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. Convert EXISTING RECREATION & STORAGE AREA TO ADU PER STATE LAW
- Permit Issued
- Issued on 3/22/2022
- Issuing Office
- Current Status
- CofO Issued on 3/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/16/2021 | CARLOS MONTES |
| Corrections Issued | 11/16/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 2/1/2022 | CARLOS MONTES |
| Plan Check Approved | 3/17/2022 | CARLOS MONTES |
| Issued | 3/22/2022 | APPLICANT |
| CofO in Progress | 12/21/2023 | MICHEL ABAJAN |
| Permit Finaled | 3/19/2024 | RUBEN SALAS |
| CofO Issued | 3/19/2024 | RUBEN SALAS |
| Permit Finaled | 3/19/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/3/2022 | AMIR KASHFI |
| Sewer availability | Cleared | 1/3/2022 | AMIR KASHFI |
| Clean Up Green Up | Cleared | 1/5/2022 | DANIEL CORONADO |
| Miscellaneous | Cleared | 1/5/2022 | DANIEL CORONADO |
| ZA Case | Cleared | 1/5/2022 | DANIEL CORONADO |
| Tenant Habitability Plan | Cleared | 1/28/2022 | MICHAEL SOTO |
| Eng Process Fee Ord 176,300 | Cleared | 2/1/2022 | AMIR KASHFI |
| Hydrant and Access approval | Cleared | 3/5/2022 | CINDY JOSSELYN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/31/2022 | Partial Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 9/23/2022 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 10/18/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 12/8/2022 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2022 | Partial Approval | MICHEL ABAJAN |
| HVAC-Rough | 12/8/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 12/8/2022 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 12/13/2022 | Approved | MICHEL ABAJAN |
| Green Building Rough | 12/13/2022 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 12/13/2022 | Approved | MICHEL ABAJAN |
| Insulation | 1/19/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 1/19/2023 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 2/2/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 11/9/2023 | Approved | MICHEL ABAJAN |
| Final | 11/9/2023 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 11/9/2023 | Approved | MICHEL ABAJAN |
| HVAC-Final | 11/9/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 11/9/2023 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 11/9/2023 | SGSOV Not Ready | MICHEL ABAJAN |
| Smoke Detectors | 11/9/2023 | Approved | MICHEL ABAJAN |
| Final | 12/7/2023 | Corrections Issued | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 12/7/2023 | SGSOV Approved | MICHEL ABAJAN |
| Final | 12/21/2023 | OK to Issue CofO | MICHEL ABAJAN |