10418 1/2 N TELFAIR AVE 91331

Certificate Information: 10418 1/2 N TELFAIR AVE 91331

Application / Permit
21016-20000-53246
Plan Check / Job No.
B21VN15631
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. Convert EXISTING RECREATION & STORAGE AREA TO ADU PER STATE LAW
Permit Issued
Issued on 3/22/2022
Issuing Office
Current Status
CofO Issued on 3/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/12/2021 APPLICANT
Assigned to Plan Check Engineer 11/16/2021 CARLOS MONTES
Corrections Issued 11/16/2021 CARLOS MONTES
Applicant returned to address corrections 2/1/2022 CARLOS MONTES
Plan Check Approved 3/17/2022 CARLOS MONTES
Issued 3/22/2022 APPLICANT
CofO in Progress 12/21/2023 MICHEL ABAJAN
Permit Finaled 3/19/2024 RUBEN SALAS
CofO Issued 3/19/2024 RUBEN SALAS
Permit Finaled 3/19/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/3/2022 AMIR KASHFI
Sewer availability Cleared 1/3/2022 AMIR KASHFI
Clean Up Green Up Cleared 1/5/2022 DANIEL CORONADO
Miscellaneous Cleared 1/5/2022 DANIEL CORONADO
ZA Case Cleared 1/5/2022 DANIEL CORONADO
Tenant Habitability Plan Cleared 1/28/2022 MICHAEL SOTO
Eng Process Fee Ord 176,300 Cleared 2/1/2022 AMIR KASHFI
Hydrant and Access approval Cleared 3/5/2022 CINDY JOSSELYN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/31/2022 Partial Inspection MICHEL ABAJAN
PLUMBING-Rough 9/23/2022 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 10/18/2022 Approved MICHEL ABAJAN
ELECTRICAL-Rough 12/8/2022 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 12/8/2022 Partial Approval MICHEL ABAJAN
HVAC-Rough 12/8/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 12/8/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 12/13/2022 Approved MICHEL ABAJAN
Green Building Rough 12/13/2022 Approved MICHEL ABAJAN
METHANE-Rough 12/13/2022 Approved MICHEL ABAJAN
Insulation 1/19/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 1/19/2023 Approved MICHEL ABAJAN
Underground Mechanical 2/2/2023 Approved MICHEL ABAJAN
ELECTRICAL-Final 11/9/2023 Approved MICHEL ABAJAN
Final 11/9/2023 Corrections Issued MICHEL ABAJAN
Green Building Final 11/9/2023 Approved MICHEL ABAJAN
HVAC-Final 11/9/2023 Approved MICHEL ABAJAN
PLUMBING-Final 11/9/2023 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 11/9/2023 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 11/9/2023 Approved MICHEL ABAJAN
Final 12/7/2023 Corrections Issued MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 12/7/2023 SGSOV Approved MICHEL ABAJAN
Final 12/21/2023 OK to Issue CofO MICHEL ABAJAN