1608 1/2 S CARMONA AVE 90019

Certificate Information: 1608 1/2 S CARMONA AVE 90019

Application / Permit
21016-20000-53080
Plan Check / Job No.
B21VN15571
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX. DETACHED GARAGE/ STORAGE BUILDING TO ACCESSORY DWELLING UNIT PER CA GOV. STATE CODE 65852.2(e)(1)(A). RE-FRAME AND RE-ROOF ENTIRE BLDG. WORK PER ENGINEER.
Permit Issued
Issued on 1/18/2022
Issuing Office
Current Status
CofO Issued on 9/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/10/2021 APPLICANT
Assigned to Plan Check Engineer 11/23/2021 ROSENDO MEDINA
Corrections Issued 11/26/2021 ROSENDO MEDINA
Plan Check Approved 1/18/2022 ROSENDO MEDINA
Issued 1/18/2022 APPLICANT
Building Plans Picked Up 1/20/2022 APPLICANT
CofO in Progress 8/3/2022 JOSE AVILA
Permit Finaled 9/1/2022 DEROLD HAUFF
CofO Issued 9/1/2022 DEROLD HAUFF
Permit Finaled 9/1/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/8/2021 WALLIE JONG
Roof/Waste drainage to street Cleared 12/8/2021 WALLIE JONG
Sewer availability Cleared 12/8/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 12/13/2021 WALLIE JONG

Contact Information

Contractor Labi Builders Inc; Lic. No.: 1050662-B 5404 WHITSETT AVENUE #6      VALLEY VILLAGE, CA 91607
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 8916 LONGDON AVE #C      TEMPLE CITY, CA 91780

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/28/2022 Partial Approval JOSE AVILA
Sewer 3/4/2022 Approved JOSE AVILA
ELECTRICAL-Rough 5/3/2022 Not Ready for Inspection JOSE AVILA
Footing/Foundation/Slab 5/3/2022 Corrections Issued JOSE AVILA
HVAC-Rough 5/3/2022 Not Ready for Inspection JOSE AVILA
PLUMBING-Rough 5/3/2022 Not Ready for Inspection JOSE AVILA
Footing/Foundation/Slab 5/5/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 5/6/2022 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 5/6/2022 Approved JOSE AVILA
Green Building Rough 5/6/2022 Approved JOSE AVILA
HVAC-Rough 5/6/2022 Partial Approval JOSE AVILA
METHANE-Rough 5/6/2022 Approved JOSE AVILA
PLUMBING-Rough 5/6/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 5/11/2022 Partial Approval JOSE AVILA
Interior/Exterior Lathing 5/11/2022 Approved JOSE AVILA
Insulation 5/13/2022 Approved JOSE AVILA
Drywall Nailing 5/24/2022 Approved JOSE AVILA
Interior/Exterior Lathing 5/24/2022 Approved JOSE AVILA
Shower Pan 5/24/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 7/14/2022 Approved JOSE AVILA
Final 7/14/2022 Corrections Issued JOSE AVILA
Green Building Final 7/14/2022 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 7/14/2022 SGSOV Approved JOSE AVILA
Smoke Detectors 7/14/2022 Approved JOSE AVILA
Final 7/19/2022 Corrections Issued JOSE AVILA
Final 7/26/2022 OK to Issue CofO JOSE AVILA