14811 W SUTTON ST 91403

Certificate Information: 14811 W SUTTON ST 91403

Application / Permit
21016-20000-53073
Plan Check / Job No.
B21VN15568
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED INT/EXT REMODEL TO EX 2-STORY SFD W/ ATT GARAGE: @1ST FLR - REMOVE WALL BETWEEN KITCHEN & DINING RM TO CREATE ONE OPEN KITCHEN/DINING AREA. REMODEL KITCHEN. REMODEL BATHRM PER PLAN. @2ND FLR - REDUCE SIZE OF TWO BEDRMS TO CONSTRUCT NEW CLOSETS, BATHRMS & LAUNDRY RM PER PLAN. CONVERT EX BATHRM INTO BEDRM.
Permit Issued
Issued on 3/17/2022
Issuing Office
Current Status
Permit Finaled on 10/26/2022

Permit Application Status History

Submitted 11/12/2021 APPLICANT
Assigned to Plan Check Engineer 11/24/2021 HAYATO TSUCHIYA
Corrections Issued 11/26/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 1/19/2022 TSE MING HUANG
Plan Check Approved 2/23/2022 HAYATO TSUCHIYA
Building Plans Picked Up 2/28/2022 APPLICANT
Issued 3/17/2022 APPLICANT
Permit Finaled 10/25/2022 MISAEL ESPARZA

Permit Application Clearance Information

Sewer availability Cleared 12/8/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/13/2021 CARLOS AGUILERA
Grading Pre-Inspection Cleared 2/3/2022 TIMOTHY POWELL

Contact Information

Contractor Bede Sierra R; Lic. No.: 1079153-B 4441 WOODMAN AVENUE #207      SHERMAN OAKS, CA 91423
Engineer Ghavimi,, Rassoul Daneshvar; Lic. No.: C48282 7007 SHADETREE LANE      WEST HILLS, CA 91307

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/23/2022 Conditional Approval MICHAEL TEMPLE
Footing/Foundation/Slab 3/24/2022 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 3/30/2022 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 4/11/2022 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 4/11/2022 Corrections Issued MISAEL ESPARZA
HVAC-Rough 4/11/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 4/11/2022 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 4/22/2022 Approved MISAEL ESPARZA
ELECTRICAL-Rough 4/22/2022 Approved MISAEL ESPARZA
HVAC-Rough 4/22/2022 Approved MISAEL ESPARZA
Drywall Nailing 4/29/2022 Partial Approval ASHLEY THOMPSON
Insulation 4/29/2022 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 4/29/2022 Partial Approval ASHLEY THOMPSON
Shower Pan 4/29/2022 Approved ASHLEY THOMPSON
Drywall Nailing 5/3/2022 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 5/11/2022 Approved MISAEL ESPARZA
Final 10/11/2022 Corrections Issued ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 10/11/2022 SGSOV Approved ROBERT GOLD
Smoke Detectors 10/11/2022 Not Ready for Inspection ROBERT GOLD
Final 10/25/2022 Permit Finaled MISAEL ESPARZA
Smoke Detectors 10/25/2022 Approved MISAEL ESPARZA