3900 N SCADLOCK LANE 91403

Certificate Information: 3900 N SCADLOCK LANE 91403

Application / Permit
21016-20000-53023
Plan Check / Job No.
B21VN15545
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL TO CONVERT 1' X 4'-1" PORTION AND 22'-1" X 2' IRREG SHAPED PORTION OF GARAGE TO ENLARGE KITCHEN AND LIVING ROOM. REMODEL KITCHEN AND (E) BATHROOM. RELOCATE LAUNDRY TO GARAGE.
Permit Issued
Issued on 1/5/2022
Issuing Office
Current Status
CofO Issued on 9/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/10/2021 APPLICANT
Assigned to Plan Check Engineer 11/23/2021 JEROME MAGAT PALMA
Corrections Issued 11/25/2021 JEROME MAGAT PALMA
Plan Check Approved 1/2/2022 JEROME MAGAT PALMA
Issued 1/5/2022 APPLICANT
Building Plans Picked Up 1/6/2022 APPLICANT
CofO in Progress 9/2/2022 JACK KARGODORIAN
Permit Finaled 9/15/2022 DEROLD HAUFF
CofO Issued 9/15/2022 DEROLD HAUFF
Permit Finaled 9/15/2022 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 12/10/2021 SERGIO VALENZUELA

Contact Information

Contractor Spazio La Designs; Lic. No.: 1006766-B 10620 MAGNOLIA BLVD      NORTH HOLLYWOOD, CA 91601
Engineer Karapetian,, Arbi; Lic. No.: C79953 21520 BURBANK BLVD APT 219      WOODLAND HILLS, CA 91367

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/1/2022 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 6/7/2022 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 6/28/2022 Partial Approval HERBERT GIRON
ELECTRICAL-Rough 6/28/2022 Approved HERBERT GIRON
Green Building Rough 6/28/2022 Not Ready for Inspection HERBERT GIRON
HVAC-Rough 6/28/2022 Approved HERBERT GIRON
MERV13>=Rough 6/28/2022 Not Ready for Inspection HERBERT GIRON
PLUMBING-Rough 6/28/2022 Approved HERBERT GIRON
Rough-Elec/Plmb/HVAC 6/28/2022 Approved HERBERT GIRON
BUILDING-Rough-Frame 7/5/2022 Corrections Issued JACK KARGODORIAN
Interior/Exterior Lathing 7/5/2022 Partial Approval JACK KARGODORIAN
Shower Pan 7/5/2022 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 7/8/2022 Approved JACK KARGODORIAN
Drywall Nailing 7/8/2022 Approved JACK KARGODORIAN
Green Building Rough 7/8/2022 Approved JACK KARGODORIAN
Interior/Exterior Lathing 7/8/2022 Approved JACK KARGODORIAN
MERV13>=Rough 7/8/2022 Approved JACK KARGODORIAN
Final 8/30/2022 Corrections Issued JACK KARGODORIAN
Green Building Final 8/30/2022 Approved JACK KARGODORIAN
MERV13>=Final 8/30/2022 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 8/30/2022 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 8/30/2022 Approved JACK KARGODORIAN
Final 9/2/2022 OK to Issue CofO JACK KARGODORIAN