18147 W VENTURA BLVD 91356
Certificate Information: 18147 W VENTURA BLVD 91356
- Application / Permit
- 21016-20000-52705
- Plan Check / Job No.
- B21VN15376
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Massage Parlor
- Work Description
- Change of use from Retail to Massage/ Therapy INTERIOR REMODEL NEW LAUNDRY AREA AND TOILET NEW 4 MASSAGE THERAPY ROOMS AND OFFICE
- Permit Issued
- Issued on 3/22/2022
- Issuing Office
- Current Status
- CofO Issued on 1/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2021 | JOE VO |
| Corrections Issued | 11/12/2021 | JOE VO |
| Applicant returned to address corrections | 12/9/2021 | JOE VO |
| Plan Check Approved | 3/1/2022 | JOE VO |
| Issued | 3/22/2022 | APPLICANT |
| CofO in Progress | 1/30/2024 | BRIAN KELLY |
| Permit Finaled | 1/30/2024 | JEFFREY DURAN |
| CofO Issued | 1/30/2024 | JEFFREY DURAN |
| Permit Finaled | 1/30/2024 | JEFFREY DURAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/22/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 1/24/2022 | JOSE DUARTE-DIAZ |
| "D" conditions | Cleared | 1/25/2022 | ANACANY HURTADO |
| ZA Case | Cleared | 1/25/2022 | ANACANY HURTADO |
| Specific Plan | Cleared | 1/26/2022 | CORREY KITCHENS |
| Green Code | Cleared | 1/27/2022 | JOE VO |
| DAS Clearance | Cleared | 3/22/2022 | JOE VO |
Contact Information
| Contractor | Jen'S Construction Inc; Lic. No.: 897784-B | 5612 HUDDART AVENUE ARCADIA, CA 91006 |
| Engineer | Chiang,, Tzuu Pien; Lic. No.: NA72618 | , |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 5/17/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Pre-Inspection | 7/1/2022 | Partial Inspection | CAMERON CHABAN |
| Pre-Inspection | 10/19/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Wood Frame | 10/19/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Wood Frame | 6/6/2023 | Partial Approval | BRIAN KELLY |
| Drywall Nailing | 6/28/2023 | Approved | BRIAN KELLY |
| T-Bar Ceiling | 6/28/2023 | Not Ready for Inspection | BRIAN KELLY |
| T-Bar Ceiling | 6/29/2023 | Corrections Issued | BRIAN KELLY |
| T-Bar Ceiling | 7/7/2023 | Approved | BRIAN KELLY |
| Final | 11/14/2023 | Not Ready for Inspection | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 11/14/2023 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 11/14/2023 | No Access for Inspection | BRIAN KELLY |
| Wood Frame | 11/14/2023 | Approved | BRIAN KELLY |
| Final | 1/22/2024 | OK to Issue CofO | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 1/22/2024 | SGSOV Approved | BRIAN KELLY |
| Smoke Detectors | 1/22/2024 | Approved | BRIAN KELLY |
| Special/Order Compliance | 1/22/2024 | Partial Inspection | MELVIN GIRTON |