4315 E YORK BLVD 90041
Certificate Information: 4315 E YORK BLVD 90041
- Application / Permit
- 21016-20000-50355
- Plan Check / Job No.
- B21VN15136
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REPAIR THE DETACHED GARAGE
- Permit Issued
- Issued on 7/22/2022
- Issuing Office
- Current Status
- Permit Finaled on 12/31/2022
Permit Application Status History
| Submitted | 11/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/5/2021 | JESSE ARELLANO |
| Corrections Issued | 11/9/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 2/3/2022 | JESSE ARELLANO |
| Applicant returned to address corrections | 3/9/2022 | JESSE ARELLANO |
| Plan Check Approved | 3/25/2022 | JESSE ARELLANO |
| Building Plans Picked Up | 4/11/2022 | APPLICANT |
| Issued | 7/22/2022 | APPLICANT |
| Permit Finaled | 12/30/2022 | CRAIG VAUGHAN |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/22/2021 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2022 | JEANETTE VONG |
Contact Information
| Contractor | Green Air Solutions Inc; Lic. No.: 1004432-B | 7640 BURNET AVENUE UNIT A VAN NUYS, CA 91405 |
| Engineer | Schwartzberg,, Leo Joshua; Lic. No.: C51851 | 7547 SEDGEWICK CT WEST HILLS, CA 91304 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/26/2022 | Conditional Approval | CRAIG VAUGHAN |
| Pre-Inspection | 7/28/2022 | Approved | CRAIG VAUGHAN |
| Reinforced Concrete Frame | 7/28/2022 | Approved | CRAIG VAUGHAN |
| Wall Anchors | 7/28/2022 | Approved | CRAIG VAUGHAN |
| Deputy Drilled-In Anchors | 7/29/2022 | Conditional Approval | CRAIG VAUGHAN |
| Deputy Drilled-In Anchors | 8/19/2022 | Conditional Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 8/30/2022 | Partial Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 9/9/2022 | Partial Approval | SCOTT FINNILA |
| Final | 10/25/2022 | Not Ready for Inspection | JULIAN AMAYA |
| SGSOV-Seismic Gas S/O Valve | 10/25/2022 | SGSOV Not Ready | JULIAN AMAYA |
| Smoke Detectors | 10/25/2022 | Not Ready for Inspection | JULIAN AMAYA |
| Special/Order Compliance | 10/25/2022 | Not Ready for Inspection | JULIAN AMAYA |
| Final | 10/31/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 10/31/2022 | SGSOV Approved | BRIAN SULLIVAN |
| Smoke Detectors | 10/31/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Special/Order Compliance | 10/31/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Final | 12/12/2022 | Corrections Issued | BRENDAN MORELLI |
| Smoke Detectors | 12/12/2022 | Partial Inspection | BRENDAN MORELLI |
| Final | 12/30/2022 | Permit Finaled | CRAIG VAUGHAN |
| Smoke Detectors | 12/30/2022 | Approved | CRAIG VAUGHAN |