8800 W PICO BLVD 90035

Certificate Information: 8800 W PICO BLVD 90035

Application / Permit
21016-20000-50351
Plan Check / Job No.
B21VN15134
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Produce Market
Work Description
REMODEL & CHANGE OF USE FROM (E) 3942 RETAIL TO (N) RETAIL MARKET W/171SF DELI SEATING, AND INSTALL 2 WALK-IN-COOLER AND 2 WALK-IN FREEZER [SEPARATE M.E.P. PERMITS REQUIRED].
Permit Issued
Issued on 5/9/2022
Issuing Office
Current Status
CofO Issued on 9/20/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/17/2021 APPLICANT
Assigned to Plan Check Engineer 11/24/2021 DAWN MC NULTY
Disabled Access Plans Picked Up 12/6/2021 APPLICANT
Corrections Issued 12/8/2021 DAWN MC NULTY
Quality Review Completed 12/10/2021 STEVEN KIM
Building Plans Picked Up 12/20/2021 APPLICANT
Applicant returned to address corrections 4/6/2022 DAWN MC NULTY
Applicant returned to address corrections 4/7/2022 DAWN MC NULTY
Plan Check Approved 4/8/2022 DAWN MC NULTY
Issued 5/9/2022 APPLICANT
CofO in Progress 8/30/2022 SORIN CIRSTOIU
Permit Finaled 9/20/2022 DAVID TSAU
CofO Issued 9/20/2022 DAVID TSAU
Permit Finaled 9/20/2022 DAVID TSAU

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/3/2022 WALLIE JONG
Food Service Establishment Cleared 2/16/2022 JASH PATEL
Sewer availability Cleared 2/25/2022 TREVOR QUAN
Comm Cor/Mini-Mall Cleared 3/7/2022 LOUIS ORTEGA
Comm Cor/Mini-Mall Cleared 3/7/2022 LOUIS ORTEGA
Food establishment approval Cleared 3/11/2022 LACDHS APPROVED
DAS Clearance Cleared 3/31/2022 NORLITO MEDRANO

Contact Information

Contractor Southwest Construction And Home Improvement; Lic. No.: 831043-B 2729 S ROBERTSON BLVD      LOS ANGELES, CA 90034

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/11/2022 Approved PAUL DAVIDSON
METHANE-Final 8/16/2022 Not Ready for Inspection SORIN CIRSTOIU
METHANE-Rough 8/16/2022 Not Ready for Inspection SORIN CIRSTOIU
Reinforced Masonry Frame 8/16/2022 Not Ready for Inspection SORIN CIRSTOIU
SGSOV-Seismic Gas S/O Valve 8/16/2022 SGSOV Not Ready SORIN CIRSTOIU
Smoke Detectors 8/16/2022 Not Ready for Inspection SORIN CIRSTOIU
Final 8/18/2022 Not Ready for Inspection SORIN CIRSTOIU
Final 8/22/2022 Not Ready for Inspection SORIN CIRSTOIU
METHANE-Final 8/22/2022 Not Ready for Inspection SORIN CIRSTOIU
METHANE-Rough 8/22/2022 Not Ready for Inspection SORIN CIRSTOIU
Reinforced Masonry Frame 8/22/2022 Not Ready for Inspection SORIN CIRSTOIU
SGSOV-Seismic Gas S/O Valve 8/22/2022 SGSOV Not Ready SORIN CIRSTOIU
Smoke Detectors 8/22/2022 Approved SORIN CIRSTOIU
Final 8/30/2022 OK to Issue CofO SORIN CIRSTOIU
METHANE-Final 8/30/2022 Approved SORIN CIRSTOIU
METHANE-Rough 8/30/2022 Approved SORIN CIRSTOIU
Reinforced Masonry Frame 8/30/2022 Approved SORIN CIRSTOIU
SGSOV-Seismic Gas S/O Valve 8/30/2022 SGSOV Approved SORIN CIRSTOIU