14810 W NEEDLES ST 91343
Certificate Information: 14810 W NEEDLES ST 91343
- Application / Permit
- 21016-20000-48186
- Plan Check / Job No.
- B21VN14870
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO (E) KITCHEN TO REMOVE LOAD BEARING WALL AND REPLACE SLIDING ROOM IN (E) DINING ROOM. ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 11/8/2021
- Issuing Office
- Current Status
- Permit Finaled on 2/23/2022
Permit Application Status History
| Submitted | 10/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/1/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 11/1/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 11/1/2021 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 11/2/2021 | APPLICANT |
| Issued | 11/8/2021 | APPLICANT |
| Permit Finaled | 2/22/2022 | MICHAEL TEMPLE |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | R L Remodeling Inc; Lic. No.: 885032-B | 22817 VENTURA BLVD #852 WOODLAND HILLS, CA 91364 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/3/2021 | Conditional Approval | MICHAEL TEMPLE |
| BUILDING-Rough-Frame | 12/9/2021 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 12/9/2021 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 12/22/2021 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 12/22/2021 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 12/22/2021 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 1/3/2022 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 1/3/2022 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 1/3/2022 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 1/6/2022 | Conditional Approval | MICHAEL TEMPLE |
| ELECTRICAL-Rough | 1/6/2022 | Corrections Issued | MICHAEL TEMPLE |
| PLUMBING-Rough | 1/6/2022 | Corrections Issued | MICHAEL TEMPLE |
| Final | 2/8/2022 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 2/8/2022 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 2/8/2022 | Approved | JENNIFER RABUCHIN |
| Final | 2/22/2022 | Permit Finaled | MICHAEL TEMPLE |