10902-10904 N ELDORA AVE 91040

Certificate Information: 10902-10904 N ELDORA AVE 91040

Application / Permit
21016-20000-48054
Plan Check / Job No.
B21VN14848
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EX ATT GARAGE (20'x20'),400 SQFT INTO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). DESIGN PER ENGR. SEE COMMENTS.
Permit Issued
Issued on 8/5/2022
Issuing Office
Valley
Current Status
CofO Issued on 12/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/15/2021 APPLICANT
Assigned to Plan Check Engineer 11/24/2021 HAYATO TSUCHIYA
Corrections Issued 11/26/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 7/16/2022 HAYATO TSUCHIYA
Building Plans Picked Up 7/19/2022 APPLICANT
Plan Check Approved 8/1/2022 PETER MOSESIAN
Issued 8/5/2022 APPLICANT
CofO in Progress 12/6/2022 WILLIAM WREN
CofO in Progress 12/6/2022 WILLIAM WREN
No Progress 12/6/2022 WILLIAM WREN
CofO in Progress 12/6/2022 WILLIAM WREN
CofO in Progress 12/6/2022 DAVID MATSON
CofO in Progress 12/7/2022 WILLIAM WREN
Permit Finaled 12/17/2022 MICHAEL SMITH
CofO Issued 12/17/2022 MICHAEL SMITH
Permit Finaled 12/17/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/10/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 3/10/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 3/15/2022 DAGOVERTO GUERRERO
Watercourse Cleared 3/15/2022 DAGOVERTO GUERRERO
Grading Pre-Inspection Cleared 7/16/2022 HAYATO TSUCHIYA

Contact Information

Contractor Owner-Builder       ,
Engineer Torres,, Efren Santos; Lic. No.: S2340 16003 S INDIAN CREEK RD      CERRITOS, CA 90701

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 9/13/2022 Partial Approval MATTHEW NELSON
PLUMBING-Rough 9/13/2022 Partial Approval MATTHEW NELSON
Deputy Drilled-In Anchors 9/22/2022 Conditional Approval MATTHEW NELSON
Footing/Foundation/Slab 9/23/2022 Approved MATTHEW NELSON
Underground Mechanical 9/27/2022 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 10/13/2022 Approved MATTHEW NELSON
ELECTRICAL-Rough 10/13/2022 Approved MATTHEW NELSON
Green Building Rough 10/13/2022 Approved MATTHEW NELSON
HVAC-Rough 10/13/2022 Approved MATTHEW NELSON
PLUMBING-Rough 10/13/2022 Approved MATTHEW NELSON
Insulation 10/17/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 10/17/2022 Approved MATTHEW NELSON
Drywall Nailing 10/25/2022 Approved MATTHEW NELSON
Final 11/30/2022 No Access for Inspection WILLIAM WREN
Green Building Final 11/30/2022 Approved WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 11/30/2022 SGSOV Not Ready WILLIAM WREN
Smoke Detectors 11/30/2022 Approved WILLIAM WREN
Final 12/5/2022 Conditional Approval WILLIAM WREN
Gas Test 12/5/2022 Approved WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 12/5/2022 SGSOV Approved WILLIAM WREN
Final 12/6/2022 OK to Issue CofO WILLIAM WREN