3469 N WRIGHTWOOD DR 91604

Certificate Information: 3469 N WRIGHTWOOD DR 91604

Application / Permit
21016-20000-48043
Plan Check / Job No.
B21VN14844
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL TO THE (E) DWELLING. REMODEL KITCHEN AND BATHROOMS. ADD NEW BEDROOM. REMOVE WALLS AND ADD NEW BEAM/POSTS. ADD NEW WINDOWS/DOORS. ALL WORK PER ENG
Permit Issued
Issued on 6/29/2022
Issuing Office
Current Status
Permit Finaled on 8/24/2023

Permit Application Status History

Submitted 11/1/2021 APPLICANT
Assigned to Plan Check Engineer 11/10/2021 JEFFREY TANGONAN
Corrections Issued 11/10/2021 JEFFREY TANGONAN
Plan Check Approved 1/27/2022 JEFFREY TANGONAN
Building Plans Picked Up 1/28/2022 APPLICANT
Issued 6/29/2022 APPLICANT
Permit Finaled 8/24/2023 CHRISTOPHE COCHRAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/7/2021 JOSE DUARTE-DIAZ
Sewer availability Cleared 12/8/2021 JOSE DUARTE-DIAZ
Specific Plan Cleared 1/11/2022 OLGA AYALA
Grading Pre-Inspection Cleared 1/27/2022 JEFFREY TANGONAN

Contact Information

Contractor Build Method Construction Inc; Lic. No.: 1059684-B 12117 VALLEYHEART DRIVE   SUITE 305    STUDIO CITY, CA 91604
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/2/2022 Conditional Approval CHRISTOPHE COCHRAN
Footing/Foundation/Slab 9/15/2022 Approved ALAN MORELOS
Underground Mechanical 9/15/2022 Approved ALAN MORELOS
ELECTRICAL-Rough 9/30/2022 Approved CHRISTOPHE COCHRAN
HVAC-Rough 9/30/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Rough 9/30/2022 Corrections Issued CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 10/6/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Rough 10/6/2022 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 10/6/2022 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 10/21/2022 Approved CHRISTOPHE COCHRAN
Insulation 10/21/2022 Approved CHRISTOPHE COCHRAN
Drywall Nailing 10/31/2022 Approved CHRISTOPHE COCHRAN
Shower Pan 10/31/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Interior/Exterior Lathing 11/3/2022 Partial Approval CHRISTOPHE COCHRAN
Shower Pan 11/3/2022 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 7/21/2023 Approved CHRISTOPHE COCHRAN
Final 7/21/2023 Corrections Issued CHRISTOPHE COCHRAN
HVAC-Final 7/21/2023 Approved CHRISTOPHE COCHRAN
PLUMBING-Final 7/21/2023 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 7/21/2023 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 7/21/2023 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 8/24/2023 Approved CHRISTOPHE COCHRAN
Final 8/24/2023 Permit Finaled CHRISTOPHE COCHRAN
HVAC-Final 8/24/2023 Approved CHRISTOPHE COCHRAN
PLUMBING-Final 8/24/2023 Approved CHRISTOPHE COCHRAN