7417 N VAN NUYS BLVD 91405

Certificate Information: 7417 N VAN NUYS BLVD 91405

Application / Permit
21016-20000-48034
Plan Check / Job No.
B21VN14843
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
*ePlan Check* Tenant improvement for an existing commercial building, new tenant Dollar Tree. Work includes; partitions, walk-in cooler/freezer, office renovations, storage shelving( 8ft max height), New openings in exterior CMU walls
Permit Issued
Issued on 4/25/2023
Issuing Office
Current Status
Permit Finaled on 7/7/2025

Permit Application Status History

Submitted 10/28/2021 APPLICANT
Assigned to Plan Check Engineer 11/18/2021 ARSALAN SHABESTARI
Corrections Issued 11/21/2021 ARSALAN SHABESTARI
Quality Review Completed 11/26/2021 HERNAN ARREOLA
Plan Check Approved 2/1/2022 ARSALAN SHABESTARI
No Progress 4/20/2023 ARSALAN SHABESTARI
Plan Check Approved 4/20/2023 ARSALAN SHABESTARI
Issued 4/25/2023 APPLICANT
Permit Finaled 7/7/2025 ANDREW DORSO

Permit Application Clearance Information

ZA Case Cleared 11/29/2021 RUBEN VASQUEZ
ZA Case Cleared 11/29/2021 RUBEN VASQUEZ
Green Code Cleared 12/21/2021 AARON COSTA
DAS Clearance Cleared 1/20/2022 ARSALAN SHABESTARI
Food establishment approval Cleared 2/1/2022 LACDHS APPROVED

Contact Information

Contractor Stitt J M Construction Inc; Lic. No.: 696272-B       ,

Inspector Information

SEAN GRIFFITH, (818) 374-1102 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/10/2025 Not Ready for Inspection ANDREW DORSO
Drywall Nailing 3/12/2025 Partial Approval GREGORY POMISH
Light Gage Steel Frame 3/14/2025 Partial Approval DEANDRE HOFFMAN
Deputy Drilled-In Anchors 3/18/2025 Conditional Approval JEFFREY DURAN
Drywall Nailing 3/18/2025 Partial Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 3/19/2025 Approved KENNETH ROBERTS
Light Gage Steel Frame 3/24/2025 Not Ready for Inspection ANDREW DORSO
T-Bar Ceiling 3/24/2025 Not Ready for Inspection ANDREW DORSO
Light Gage Steel Frame 3/25/2025 Approved BRIAN KELLY
T-Bar Ceiling 4/2/2025 Not Ready for Inspection GREGORY POMISH
T-Bar Ceiling 4/15/2025 Not Ready for Inspection GREGORY POMISH
T-Bar Ceiling 4/17/2025 Approved DEANDRE HOFFMAN
Final 6/9/2025 Not Ready for Inspection DANIEL VARNUM
Green Building Final 6/9/2025 Not Ready for Inspection DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 6/9/2025 SGSOV Not Ready DANIEL VARNUM
Smoke Detectors 6/9/2025 Not Ready for Inspection DANIEL VARNUM
Deputy Drilled-In Anchors 6/10/2025 Approved JOHN KITCKO
Final 6/27/2025 Partial Inspection ANDREW DORSO
Green Building Final 6/27/2025 Approved ANDREW DORSO
SGSOV-Seismic Gas S/O Valve 6/27/2025 SGSOV Approved ANDREW DORSO
Smoke Detectors 6/27/2025 Approved ANDREW DORSO
Final 7/2/2025 Partial Inspection BRIAN KELLY
Final 7/7/2025 Permit Finaled ANDREW DORSO