10837 W VIA VERONA 90077
Certificate Information: 10837 W VIA VERONA 90077
- Application / Permit
- 21016-20000-47948
- Plan Check / Job No.
- B21VN14824
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL KITCHEN AND BATHROOMS. REMOVE WALLS AND ADD NEW BEAMS. ALL WORK PER ENG.
- Permit Issued
- Issued on 1/20/2022
- Issuing Office
- Current Status
- Permit Finaled on 12/2/2022
Permit Application Status History
| Submitted | 11/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2021 | JEFFREY TANGONAN |
| Corrections Issued | 11/9/2021 | JEFFREY TANGONAN |
| Issued | 1/20/2022 | APPLICANT |
| Building Plans Picked Up | 2/28/2022 | APPLICANT |
| Permit Finaled | 12/1/2022 | CHRISTOPHER WILSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/10/2021 | SERGIO VALENZUELA |
Contact Information
| Contractor | Repipe 1 Restoration Inc; Lic. No.: 1003868-B | 19326 VENTURA BLVD STE 200 TARZANA, CA 91356 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 2/8/2022 | No Access for Inspection | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 2/8/2022 | No Access for Inspection | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 2/8/2022 | No Access for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 2/8/2022 | No Access for Inspection | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 2/9/2022 | Partial Approval | BRENDAN LOONEY |
| HVAC-Rough | 2/9/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 2/9/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| HVAC-Rough | 2/14/2022 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 2/14/2022 | Approved | JOHN KIDWELL |
| Shower Pan | 2/16/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Pre-Inspection | 2/17/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Insulation | 2/25/2022 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 3/1/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Deputy Drilled-In Anchors | 3/2/2022 | Approved | MICHAEL PELHAM |
| ELECTRICAL-Rough | 3/7/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 3/7/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 3/11/2022 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 3/11/2022 | Partial Approval | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 3/16/2022 | Corrections Issued | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 3/21/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 3/21/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 3/22/2022 | Approved | CHRISTOPHER WILSON |
| Insulation | 3/25/2022 | Partial Approval | CHRISTOPHER WILSON |
| Drywall Nailing | 4/5/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Drywall Nailing | 4/7/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Drywall Nailing | 4/12/2022 | Approved | DANIEL ORRANTE |
| Insulation | 7/12/2022 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 7/12/2022 | Partial Approval | STEPHANIE SWANSON |
| ELECTRICAL-Final | 11/3/2022 | Corrections Issued | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 11/3/2022 | SGSOV Approved | CHRISTOPHER WILSON |
| Smoke Detectors | 11/3/2022 | Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 11/17/2022 | Approved | CHRISTOPHER WILSON |
| Final | 11/17/2022 | Corrections Issued | CHRISTOPHER WILSON |
| HVAC-Final | 11/17/2022 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Final | 11/17/2022 | Approved | CHRISTOPHER WILSON |
| Final | 11/29/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Final | 12/1/2022 | Permit Finaled | CHRISTOPHER WILSON |
| Pre-Inspection | 12/1/2022 | Approved | CHRISTOPHER WILSON |