5045 N DONNA AVE 91356
Certificate Information: 5045 N DONNA AVE 91356
- Application / Permit
- 21016-20000-47451
- Plan Check / Job No.
- B21VN14781
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- CONVERT 5'-6" X 7'-4" PORTION OF PATIO COVER/LANAI TO FULL BATHROOM (EXTERIOR ACCESS ONLY).
- Permit Issued
- Issued on 2/25/2022
- Issuing Office
- Current Status
- CofO Issued on 9/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/5/2021 | RAPHAEL ROSAS |
| Corrections Issued | 11/5/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 11/19/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 1/10/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 2/15/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 2/17/2022 | APPLICANT |
| Issued | 2/25/2022 | APPLICANT |
| CofO in Progress | 8/30/2022 | DAVID SANDOVAL |
| CofO Issued | 9/10/2022 | MICHAEL SMITH |
| Permit Finaled | 9/10/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/28/2022 | Corrections Issued | DAVID SANDOVAL |
| Wood Frame | 4/28/2022 | Corrections Issued | DAVID SANDOVAL |
| Underground Mechanical | 5/2/2022 | Partial Approval | DAVID SANDOVAL |
| Underground Mechanical | 5/9/2022 | Approved | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2022 | Partial Approval | DAVID SANDOVAL |
| ELECTRICAL-Rough | 6/24/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| HVAC-Rough | 6/24/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 6/24/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Interior/Exterior Lathing | 6/28/2022 | Partial Approval | DAVID SANDOVAL |
| Insulation | 6/30/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Shower Pan | 6/30/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Drywall Nailing | 7/1/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Interior/Exterior Lathing | 7/1/2022 | Partial Approval | DAVID SANDOVAL |
| Drywall Nailing | 7/5/2022 | Approved | MORRIS JACKSON |
| Shower Pan | 7/5/2022 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 7/20/2022 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 7/20/2022 | Approved | VINCENT HANLEY |
| Final | 7/20/2022 | Partial Inspection | VINCENT HANLEY |
| HVAC-Final | 7/20/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 7/20/2022 | Approved | VINCENT HANLEY |
| Smoke Detectors | 7/20/2022 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 7/27/2022 | Approved | MORRIS JACKSON |
| Final | 7/27/2022 | Partial Inspection | MORRIS JACKSON |
| HVAC-Final | 7/27/2022 | Approved | MORRIS JACKSON |
| PLUMBING-Final | 7/27/2022 | Approved | MORRIS JACKSON |
| Final | 8/30/2022 | OK to Issue CofO | DAVID SANDOVAL |