11227 N DEMPSEY AVE 91344

Certificate Information: 11227 N DEMPSEY AVE 91344

Application / Permit
21016-20000-47436
Plan Check / Job No.
B21VN14776
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) 21' X 21' DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2 (e)(1)(A). ALL WORK PER WFPP.
Permit Issued
Issued on 9/14/2022
Issuing Office
Valley
Current Status
CofO Issued on 10/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/1/2021 APPLICANT
Assigned to Plan Check Engineer 11/8/2021 PARISA ZAHABI
Corrections Issued 11/8/2021 PARISA ZAHABI
Applicant returned to address corrections 12/8/2021 PARISA ZAHABI
Plan Check Approved 1/12/2022 ALFREDO JARA
Building Plans Picked Up 1/13/2022 APPLICANT
Issued 9/14/2022 APPLICANT
CofO in Progress 9/8/2024 JENNIFER RABUCHIN
CofO Issued 10/25/2024 DANIEL ORRANTE
Permit Finaled 10/25/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 12/1/2021 JOSE DUARTE-DIAZ
Construction near power lines Cleared 12/1/2021 WALTER RAMIREZ
Sewer availability Cleared 12/1/2021 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 12/2/2021 JOSE DUARTE-DIAZ
GPI Written Notices Cleared 1/12/2022 PARISA ZAHABI

Contact Information

Contractor Q Construction Inc; Lic. No.: 1023970-B 9671 SUNLAND BLVD SUITE 2A      SHADOW HILLS, CA 91040

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/26/2022 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 9/26/2022 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 9/28/2022 Approved JENNIFER RABUCHIN
PLUMBING-Rough 9/28/2022 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 10/14/2022 Corrections Issued JENNIFER RABUCHIN
Gas Test 10/14/2022 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 10/14/2022 Approved JENNIFER RABUCHIN
Wood Frame 10/14/2022 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 10/20/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 10/20/2022 Approved JENNIFER RABUCHIN
Green Building Rough 10/20/2022 Approved JENNIFER RABUCHIN
HVAC-Rough 10/20/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 10/20/2022 Partial Approval JENNIFER RABUCHIN
Insulation 10/25/2022 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 10/27/2022 Approved JENNIFER RABUCHIN
Drywall Nailing 10/31/2022 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 12/2/2022 SGSOV Not Ready JENNIFER RABUCHIN
ELECTRICAL-Final 1/27/2023 Corrections Issued JENNIFER RABUCHIN
Final 1/27/2023 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 1/27/2023 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 1/27/2023 Approved JENNIFER RABUCHIN
Final 2/3/2023 Not Ready for Inspection ROBERT GOLD
Final 7/18/2024 Corrections Issued JENNIFER RABUCHIN
Service/Power Release 7/18/2024 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Final 9/6/2024 Approved JENNIFER RABUCHIN
Final 9/6/2024 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 9/6/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 9/6/2024 Approved JENNIFER RABUCHIN
Service/Power Release 9/6/2024 Approved JENNIFER RABUCHIN